NASCLA Commercial General Building Contractor
The nationally recognized exam for commercial general building contractors, accepted by 15+ states. Covers project management, estimating, safety, contracts, financial management, and construction methods.
Content Areas
Project Management
Project scheduling (CPM, Gantt), resource allocation, subcontractor coordination, quality control, and project closeout.
129Q available · 22% weight
Estimating
Quantity takeoff, material/labor/equipment cost estimation, overhead & profit, bid preparation.
70Q available · 18% weight
Safety & OSHA
OSHA 29 CFR 1926, fall protection, excavation safety, scaffolding, hazard communication, PPE, confined space.
56Q available · 15% weight
Contract Law & Documents
Contract types, AIA documents, change orders, payment applications, bonds, dispute resolution.
67Q available · 15% weight
Financial Management
Job cost accounting, cash flow, financial statements, payroll, taxes, depreciation, insurance.
57Q available · 15% weight
Plans, Specs & Codes
Drawing interpretation, CSI MasterFormat, IBC building codes, ADA, shop drawings and submittals.
50Q available · 10% weight
Construction Methods & Materials
Concrete, masonry, structural steel, wood framing, roofing, earthwork.
71Q available · 5% weight
Practice Questions
Project Management
129QIn a Critical Path Method (CPM) schedule, Activity A has a duration of 5 days, Activity B has a duration of 8 days, and Activity C has a duration of 3 days. Activities A and B can start simultaneously, and Activity C cannot start until both A and B are complete. What is the total project duration?
easyWhat information should be included in daily construction reports to provide maximum legal protection?
easyYour concrete subcontractor wants to pour a foundation when the weather forecast shows temperatures dropping to 28°F overnight. The specifications require concrete protection when temperatures fall below 32°F. What action should you take?
mediumA project has 25% float consumed in the first quarter. The project is 20% complete. What does this indicate about project schedule performance?
hardA crew of 6 workers can install 240 linear feet of electrical conduit in 8 hours. If you need to install 900 linear feet and want to complete the work in 6 hours, how many workers do you need?
hardWhat information should be included in daily construction reports?
mediumA subcontractor consistently fails to attend weekly coordination meetings despite being notified. Their work is creating conflicts with other trades. What is the most appropriate escalation?
hardWhat is typically required before a Certificate of Substantial Completion can be issued?
mediumWhich factor is most critical when determining the optimal crew size for a specific construction activity?
mediumWhat is the primary purpose of a Quality Assurance (QA) program in construction?
easyA project schedule shows Activity A (5 days) must finish before Activity B (8 days) can start, and Activity B must finish before Activity C (6 days) can start. If Activity A starts on Day 1, what is the Early Finish date for Activity C?
mediumWhich type of project documentation should be maintained to support potential delay claims?
mediumDuring project closeout, who typically has the primary responsibility for creating the initial punch list?
easyA project has 15 workers scheduled for Week 1, 22 workers for Week 2, and 18 workers for Week 3. The average hourly rate is $28, and each worker works 40 hours per week. What is the total labor budget for these three weeks?
mediumIn a Quality Control program, when should inspections be performed for concealed work such as electrical rough-in?
easyDuring project closeout, what is the typical sequence for punch list completion?
mediumWhich element is NOT typically included in a comprehensive Quality Control checklist for concrete placement?
easyA concrete crew can place 45 cubic yards per day with a 6-person crew. If 180 cubic yards of concrete need to be placed and the schedule allows 3 days, what is the minimum crew size required?
mediumHow long should daily reports and project correspondence typically be retained after project completion?
mediumA project has the following activities: A(5 days), B(8 days), C(6 days), D(4 days). Activity B starts after A, C starts after A, and D starts after both B and C are complete. What is the total project duration?
mediumIn Critical Path Method (CPM) scheduling, what is the primary purpose of calculating total float for activities?
easyA quality control inspection reveals that 15 out of 200 installed light fixtures are not functioning properly. What is the defect rate, and what action should be taken?
mediumWhen managing multiple subcontractors working in the same area, what is the MOST effective method to prevent conflicts and ensure safety?
mediumDuring a weekly subcontractor coordination meeting, the electrical subcontractor reports they cannot start rough-in work as scheduled because the framing inspection has not been completed. What is the general contractor's BEST immediate response?
mediumWhat is the primary difference between Quality Control (QC) and Quality Assurance (QA) in construction project management?
easyWhat is the primary advantage of using a resource-leveled schedule?
mediumWhich document is most appropriate for tracking daily labor productivity and equipment usage on a construction project?
easyWhich document should be used to formally communicate a change in project scope to all stakeholders?
easyA concrete crew can place 45 cubic yards per day. If a foundation requires 270 cubic yards and concrete can only be delivered on weekdays, how many work days are needed if concrete must be placed the same day it's delivered?
easyWhat is the primary advantage of using a Gantt chart over a simple activity list for project scheduling?
easy+ 99 more questions
Estimating
70QA general contractor's annual overhead is $480,000 and they typically complete $3,200,000 in annual volume. For a $125,000 project, what overhead amount should be allocated?
mediumA contractor's equipment ownership costs include depreciation, insurance, taxes, and storage. These costs are classified as:
mediumA carpentry crew's base productivity is 120 sq ft of framing per hour. Working at 15 feet above grade reduces productivity by 10%, and working in 25°F weather reduces it by another 15%. What is the adjusted hourly productivity?
hardA contractor's home office overhead includes $85,000 annual rent, $120,000 salaries, and $45,000 other expenses. If they plan $2,500,000 in annual volume, what overhead percentage should be applied to bids?
easyA contractor's annual overhead is $480,000 and they typically complete $3,200,000 in work annually. For a $150,000 project, what overhead amount should be allocated?
mediumWhich material pricing method provides the most accurate cost estimate for a project starting in 8 months?
mediumDuring a bid opening, a contractor discovers their bid is significantly lower than all others. What is the most appropriate first action?
mediumA contractor estimates that formwork for a concrete pour will cost $8,500 in materials and $12,200 in labor. If the contractor applies 18% overhead and 8% profit to all costs, what is the total bid price for this work item?
hardWhich factor is most critical when determining material waste allowances in quantity takeoffs?
mediumA contractor owns a crane that cost $120,000 with an expected life of 8 years and $20,000 salvage value. Using straight-line depreciation, what is the hourly ownership cost if the crane operates 1,200 hours annually?
mediumWhat is the standard industry practice for handling material waste in quantity takeoffs?
mediumWhich approach provides the most accurate concrete volume calculation for a foundation with multiple step-downs?
easyDuring the bid preparation process, a contractor discovers a significant discrepancy in the project drawings. What is the most appropriate action?
easyA specialty trade contractor quotes $85,000 for work that typically costs $95,000. Before accepting this quote, what should the general contractor prioritize?
hardA takeoff shows 1,250 linear feet of 2x10 lumber needed. The lumber yard sells 2x10s in 8', 12', 16', and 20' lengths. To minimize waste, what combination should be ordered?
mediumA subcontractor submits a bid of $125,000 for electrical work but has a history of 15% cost overruns. If you include a 10% contingency for this trade, what amount should you include in your estimate?
hardWhen performing a quantity takeoff for paint, which approach accounts for the most accurate coverage calculation?
hardDuring the bid preparation process, a subcontractor submits their quote 30 minutes before the bid deadline. The general contractor should:
mediumWhich factor most significantly affects productivity rates in labor cost estimation?
easyWhen measuring concrete quantities from architectural drawings, which dimension is most critical to verify with structural drawings?
mediumIn quantity takeoff, what is the primary purpose of using assemblies or systems takeoff rather than detailed component takeoff?
mediumMaterial costs for lumber have increased 15% since the original estimate was prepared 3 months ago. The original lumber cost was $28,500. If lumber represents 12% of total project cost, what is the impact on the total project cost?
mediumA supplier quotes lumber at $485 per thousand board feet (MBF). A project requires 12,500 board feet. With 8% waste factor and 6.5% sales tax, what is the total material cost?
mediumWhat is the most important consideration when determining whether to own or rent construction equipment?
mediumWhat is the primary purpose of conducting a pre-bid site visit?
easyWhen material prices are volatile, which strategy best protects a contractor during the bidding process?
mediumA masonry crew of 3 workers can lay 1,200 square feet of block wall per day. If the crew costs $85 per hour total and works 8-hour days, what is the labor cost per square foot for block installation?
mediumA complex renovation project requires specialized equipment available from only one supplier. How should this affect the equipment cost estimate?
easyA contractor is deciding between purchasing a $45,000 excavator or renting one for $350 per day. The project will require the excavator for 85 days, and the contractor estimates using it on future projects 120 days per year. What is the most cost-effective decision for the first year?
hardDuring quantity takeoff for roofing work, an estimator discovers that the architectural drawings show a different roof area than calculated from the building dimensions. What should be the next step?
medium+ 40 more questions
Safety & OSHA
56QA personal fall arrest system must be rigged so that an employee cannot free fall more than:
mediumAn excavation is 15 feet deep in Type A soil. Water seepage is evident at 8 feet depth. How does this affect the soil classification and protective requirements?
mediumA mobile scaffold is 24 feet high and 8 feet wide. What is the maximum height-to-base width ratio allowed by OSHA before the scaffold must be tied off or guyed?
mediumA trench box (trench shield) is being used in an excavation that is 12 feet deep. The shield extends to 10 feet deep. What is the maximum allowable distance the shield can extend above the bottom of the excavation?
hardAn excavation is 8 feet deep in Type B soil. A worker reports water seepage at the 6-foot level. What is the required slope ratio for this condition?
hardUnder the Globally Harmonized System (GHS), which pictogram indicates acute toxicity?
easyA competent person conducting daily scaffold inspections discovers a loose guardrail connection. What action must be taken?
easyWhat is the minimum distance that guardrails must extend beyond the last plank on a scaffold platform?
mediumA trench is being excavated in Type B soil. If the trench is 12 feet deep, what is the maximum allowable slope ratio for the sides without additional protective systems?
mediumA GFCI protection device trips repeatedly when a power tool is plugged in. The tool appears to work normally on other circuits. What is the most appropriate action?
mediumAn excavation in Type A soil is 8 feet deep. What is the steepest allowable slope angle from horizontal without requiring additional protective systems?
hardA concrete finisher is working with wet concrete containing crystalline silica. The exposure assessment shows an 8-hour TWA of 60 μg/m³. What is required based on OSHA's respirable crystalline silica standard?
hardA worker is required to wear a hard hat, safety glasses, and steel-toed boots. The employer provides all equipment except safety glasses. According to OSHA, who is responsible for providing the safety glasses?
easyA contractor discovers that an employee has been exposed to a hazardous chemical. According to OSHA's Hazard Communication Standard, what document must be immediately available to provide detailed safety information?
easyA competent person finds a crack in a scaffold plank during daily inspection. What action should be taken?
easyAn electrical circuit is locked out for maintenance, but testing reveals the circuit is still energized. What is the most likely cause and required action?
hardBefore entering a permit-required confined space, atmospheric testing must be performed in what sequence?
mediumYou are reviewing scaffold inspection records. According to OSHA, how often must scaffolds be inspected during use?
easyAccording to OSHA standards, at what height must fall protection be provided for employees working on walking/working surfaces in construction?
easyA rectangular excavation is 12 feet deep, 8 feet wide, and 20 feet long in Type B soil. What is the minimum horizontal distance required from the toe of the excavation for a simple slope?
mediumWorkers are cutting concrete with handheld power saws that generate respirable crystalline silica. What is the primary PPE requirement under OSHA's silica standard?
mediumWhich type of scaffold requires a competent person to perform daily inspections before each work shift?
easyWorkers need to enter a storage tank to perform maintenance. The tank has been emptied and ventilated. What is the minimum oxygen level required before entry without supplied air respiratory protection?
hardA contractor discovers that a subcontractor's employees are working in a 15-foot deep trench without proper protective systems. What is the contractor's immediate responsibility under OSHA regulations?
mediumA frame scaffold is being erected to a height of 32 feet. The scaffold frames are 6 feet wide. What is the maximum base width-to-height ratio allowed without requiring guy wires or ties?
hardA 480-volt electrical panel needs maintenance during construction. Who is authorized to perform lockout/tagout procedures on this equipment?
easyA new chemical product arrives on site without a Safety Data Sheet (SDS). According to OSHA's Hazard Communication Standard, what must the contractor do?
mediumA worker using a personal fall arrest system falls 8 feet before the system activates. The total fall distance including deceleration is 12 feet. Is this system compliant with OSHA standards?
hardA worker will be exposed to noise levels of 95 dBA for 4 hours during concrete demolition. According to OSHA's permissible exposure limits, what action is required?
hardDuring a confined space rescue, the attendant observes that the entrant has collapsed. What is the attendant's first priority?
medium+ 26 more questions
Contract Law & Documents
67QWhich AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
easyA payment bond covers 100% of the contract value of $3,000,000. A subcontractor is owed $85,000 but hasn't been paid. What is the maximum amount the subcontractor can claim against the payment bond?
mediumA contractor receives a change order that increases the contract value by $75,000. The original contract was $1,200,000. If retainage is 8%, how much additional retainage will be held?
easyA cost-plus contract has actual costs of $1,850,000 with a contractor fee of 6%. Additional costs due to owner-directed changes total $125,000. What is the total amount due to the contractor?
hardA contractor's indemnification clause requires them to 'hold harmless' the owner from claims arising from the contractor's negligence. The owner is sued for $500,000 due to contractor negligence and incurs $75,000 in legal fees. What is the contractor's total indemnification obligation?
mediumDuring project execution, a dispute arises between the owner and contractor regarding interpretation of contract specifications. The contract requires disputes to be resolved through binding arbitration. What is the primary advantage of arbitration over litigation?
mediumA contractor submits a guaranteed maximum price (GMP) proposal of $2,850,000 with actual costs of $2,720,000. If the contract specifies a 60/40 cost savings split (contractor/owner), what is the contractor's final compensation?
hardA subcontract agreement includes a pay-when-paid clause. The owner becomes insolvent and cannot pay the general contractor. What is the subcontractor's legal position?
hardIn a lump sum contract, the contractor discovers that the quantity of concrete work is 30% more than shown in the plans. The contract is silent on quantity variations. What is the contractor's most likely recourse?
hardIn AIA A201, who typically has the authority to reject work that does not conform to the contract documents?
mediumA project has a contract value of $3,200,000. The owner requires both performance and payment bonds. If the bond premium is 1.2% of the contract value, what is the total cost for both bonds?
mediumDuring construction, the owner requests additional work that was not included in the original contract scope. What document should the contractor prepare to formalize this change?
easyWhen a contractor provides an indemnification clause in a contract, they are agreeing to:
mediumWhen a subcontractor's work damages another subcontractor's completed work, who is typically responsible for the repair costs under standard subcontract terms?
mediumUnder a Guaranteed Maximum Price (GMP) contract, if the actual cost of work is $485,000 and the GMP is $500,000, what happens to the $15,000 difference?
mediumA contractor receives a change order that increases the contract value by $275,000 and extends the completion date by 18 days. The contractor's surety bond was originally 100% of the $4,200,000 contract value. What action should the contractor take regarding the bond?
hardWhen can a contractor typically submit a change order request for additional compensation?
easyA contractor discovers unexpected rock conditions requiring additional excavation costs of $45,000. The work was completed 15 days ago, and the contractor just realized the full cost impact today. Under typical contract terms, what should the contractor do first?
mediumAn owner-contractor agreement (AIA A101) references AIA A201 General Conditions. During construction, there appears to be a conflict between a provision in A101 and A201. Which document typically takes precedence?
hardDuring construction, the owner requests additional work valued at $125,000. The architect issues a change directive, but the contractor disputes the amount. Under typical AIA contract terms, how should the contractor proceed?
hardA contractor enters into a lump sum contract for $2,850,000 with 10% retainage held until project completion. If the contractor has submitted progress payments totaling $1,900,000 to date, what is the total amount that should have been paid by the owner?
easyIn a unit price contract for excavation at $12 per cubic yard, the estimated quantity was 5,000 cubic yards, but actual quantity was 6,200 cubic yards. What is the total payment for excavation?
easyWhat documentation is typically required to support a valid change order request?
easyWhich AIA document establishes the general conditions for the contract between owner and contractor?
easyIn AIA Document A401, which party is primarily responsible for coordinating the work of sub-subcontractors?
mediumA contractor's general liability insurance has a $2,000,000 per occurrence limit. A claim for $2,500,000 is filed. Assuming the claim is covered, what is the contractor's potential exposure?
mediumDuring a project dispute, the contract specifies mediation first, then arbitration if mediation fails. What is the main advantage of this stepped approach?
mediumA change order increases both the contract price and time for completion. For the change order to be valid and enforceable, it must be:
mediumA contractor discovers unforeseen rock excavation that will cost an additional $45,000. The change order includes 15% markup for overhead and profit. If the owner retains 10% on all work, what is the net payment to the contractor for this change order?
mediumA Time and Materials contract has a labor rate of $85/hour and materials are billed at cost plus 15%. If a repair requires 12 hours of labor and $2,400 in materials, what is the total billing?
medium+ 37 more questions
Financial Management
57QA construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
easyWhat is the primary purpose of job cost accounting in construction?
easyA construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
mediumA general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
easyWhich tax is the contractor responsible for paying entirely without any employee contribution?
mediumA general contractor has direct costs of $850,000, overhead costs of $127,500, and wants a 12% profit margin on total costs. What should be the contract price?
mediumWhich type of insurance provides coverage for injuries to employees while performing work-related duties?
easyWhich federal tax form must employers file quarterly to report income taxes withheld and FICA taxes?
mediumEquipment costing $120,000 is being depreciated using the double declining balance method over 5 years. What is the depreciation expense for the second year?
hardAn employee earning $55,000 annually works in a state with no state income tax. The employee claims 2 allowances. Which taxes must the employer withhold from the employee's paycheck?
easyA project has actual costs of $450,000 against a budget of $420,000, with 80% completion. What is the projected cost at completion using the current cost performance?
hardA contractor experiences a significant equipment breakdown that delays a project by two weeks, resulting in additional labor costs and potential penalty clauses. This situation primarily affects which aspect of financial management?
mediumA construction company's current ratio is 1.8, and its quick ratio is 1.2. This indicates that:
hardWhich scenario would most likely require a contractor to register for and collect sales tax?
mediumEquipment costing $80,000 with a useful life of 8 years and no salvage value is being depreciated using the straight-line method. After 3 years, what is the book value?
easyA general contractor discovers that actual job costs are running 15% over budget on a $2.8 million project that is 60% complete. If the trend continues, what will be the total cost overrun at project completion?
mediumA general contractor is managing a project where material costs have increased 15% above budget due to market conditions. The original material budget was $320,000. How should this variance be classified in job cost reporting?
mediumA construction company's cash flow projection shows receipts of $450,000 and disbursements of $520,000 for the month. The beginning cash balance was $95,000. What action should management prioritize?
mediumWhich type of insurance protects a contractor against claims arising from professional errors or omissions in design or specification services?
easyA general contractor is experiencing cash flow problems and considering factoring receivables. Which statement best describes this financing option?
mediumA contractor is analyzing a project where the budgeted cost is $800,000 and the actual cost to date is $650,000 with 75% of work completed. What is the projected cost at completion using the cost performance index method?
hardA contractor purchases equipment for $75,000 with a 5-year useful life and $5,000 salvage value. Using straight-line depreciation, what is the annual depreciation expense?
mediumA construction company discovers that actual labor costs on a project are running 15% over budget when 60% of the work is complete. If the original labor budget was $200,000, what is the projected final labor cost variance?
hardWhich type of insurance provides coverage for employees who are injured while performing their job duties?
easyA general contractor is experiencing cash flow problems due to slow payments from clients. Which strategy would be most effective for improving short-term cash flow?
mediumWhen tracking job costs, indirect costs such as office rent and administrative salaries should be allocated to projects using which method?
hardAn employee earns $65,000 annually. What is the employer's total FICA contribution for this employee in 2024?
mediumAn employee earns $52,000 annually. What is the employer's FICA tax obligation for this employee in 2024?
mediumA contractor has beginning cash of $45,000, cash receipts of $125,000, and cash disbursements of $138,000 for the month. What is the ending cash balance?
mediumWhich insurance type is typically required by law for construction companies with employees?
easy+ 27 more questions
Plans, Specs & Codes
50QIn CSI MasterFormat, which division covers earthwork and site preparation?
easyIn a mechanical drawing, what does 'CFM' typically measure?
easyIn CSI MasterFormat Division 08, which of the following would typically be included?
mediumOn a mechanical plan, what does the symbol 'RTU' typically indicate?
mediumAccording to CSI MasterFormat, which division covers concrete work?
easyA commercial building has a total floor area of 45,000 sq ft with an occupant load of 300 people. If the building has 4 exit doors, what is the minimum width required for each door assuming equal distribution?
mediumYour subcontractor submits shop drawings for structural steel that show a connection detail different from the contract documents. What is the appropriate action?
mediumWhich CSI MasterFormat division covers roofing and waterproofing work?
easyFor ADA compliance, what is the maximum force required to open an interior door?
hardOn a mechanical drawing, a line marked with 'S' inside a circle typically indicates what type of piping system?
mediumAccording to the IBC, what is the maximum dead-end corridor length allowed in a non-sprinklered business occupancy?
hardA contractor receives shop drawings for structural steel 45 days after submitting them. The contract allows 30 days for review. What is the most appropriate action?
mediumWhat is the standard height for accessible light switches and controls under ADA guidelines?
mediumDuring the submittal process, the architect rejects shop drawings for curtain wall systems due to inadequate structural calculations. As the general contractor, what is your next step?
mediumAccording to the IBC, what is the maximum allowable floor area per story for a Type IIB construction office building (Business Group B occupancy) without sprinklers?
mediumA mechanical engineer specifies that HVAC equipment submittals must include seismic calculations. The equipment supplier states this will add 6 weeks to delivery. What is the contractor's best course of action?
hardOn an electrical plan, a rectangle with three parallel lines inside typically represents:
easyWhen reviewing shop drawings for structural steel, what is the primary responsibility of the general contractor?
mediumDuring shop drawing review, you notice that a steel fabricator has substituted A572 Grade 50 steel for specified A36 steel. What should be your primary concern?
hardWhen reviewing shop drawings, what is the primary responsibility of the general contractor?
mediumDuring construction, an electrical contractor discovers that the panel schedule conflicts with the floor plan regarding circuit routing. What is the proper procedure for resolving this discrepancy?
hardYou are reviewing shop drawings for precast concrete panels. The drawings show connection details that differ from the structural drawings but appear to be structurally adequate. What should you do?
hardA project requires a fire-rated assembly with a 2-hour rating. You receive shop drawings showing a wall assembly with 1-hour rated components. What is your appropriate response?
mediumAn electrical panel schedule shows a 200-amp main breaker with 30 circuits each rated at 20 amps. What is the total connected load?
mediumWhich CSI MasterFormat division would typically include specifications for elevators?
easyYou receive shop drawings for custom millwork that show different wood species than specified. The architect has not yet reviewed these drawings. What is your appropriate action?
hardA foundation plan shows a footing detail with dimensions 3'-0" x 3'-0" x 1'-6" supporting a 12" x 12" column. What is the bearing pressure if the total load is 45,000 pounds?
mediumOn a structural drawing, a beam is labeled W18x50. What does the '50' represent?
easyAccording to the IBC, what is the minimum ceiling height required for occupied spaces in commercial buildings?
mediumOn architectural drawings, a dashed line typically represents:
easy+ 20 more questions
Construction Methods & Materials
71QWhat is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
hardWhat is the primary advantage of using Type S mortar over Type N mortar in masonry construction?
mediumWhat type of welding electrode classification would be most appropriate for welding structural steel in all positions?
mediumWhat is the primary advantage of using Type III (high early strength) Portland cement in commercial construction?
mediumA concrete slab requires 45 cubic yards of concrete with a water-cement ratio of 0.45. If the cement content is 6 bags per cubic yard, how many gallons of water are needed? (1 bag cement = 94 lbs, 1 gallon water = 8.34 lbs)
mediumIn structural steel construction, what does the term 'slip-critical connection' refer to?
hardDuring concrete placement on a hot summer day (95°F), the concrete temperature reaches 85°F upon delivery. What is the most appropriate immediate action?
easyAccording to typical building codes, what is the minimum slope required for positive drainage away from building foundations?
mediumWhen welding structural steel in the field, the welder's certification has expired. What is the appropriate course of action before allowing any welding to proceed?
mediumWhen welding structural steel in the field, what is the primary concern with welding in temperatures below 32°F?
mediumDuring a structural steel erection, you discover that a beam connection requires 8 high-strength bolts in double shear. Each bolt has a shear capacity of 21.6 kips per shear plane. What is the total shear capacity of this connection?
mediumIn structural steel construction, what is the primary advantage of using high-strength bolts over welding for field connections?
mediumConcrete cylinders tested at 28 days show an average compressive strength of 3,200 psi when the specified strength is 3,000 psi. However, one cylinder tested at 2,750 psi. According to ACI standards, what action is required?
hardDuring structural steel erection, a welder notices porosity in a critical connection weld. What should be the immediate course of action?
mediumWhat is the primary purpose of using air-entrained concrete in commercial construction?
easyWhat is the primary purpose of compaction testing during earthwork operations?
easyA structural steel beam connection requires 6 high-strength bolts, each with a shear capacity of 21.6 kips. If the connection must resist a factored shear load of 95 kips, what is the utilization ratio of this connection?
hardA floor system uses 2×12 joists spanning 16 feet with a live load of 125 psf. The joists are spaced 12 inches on center. What is the total load per linear foot on each joist?
hardA carpenter needs to frame a roof with a 6:12 pitch. The building is 32 feet wide with a centered ridge beam. What is the length of each rafter from the ridge to the wall plate (not including overhang)?
hardA concrete mix design calls for a water-cement ratio of 0.45. If 600 pounds of cement are used per cubic yard, what is the required weight of water per cubic yard?
easyDuring brick installation on a commercial building facade, the mason notices efflorescence appearing on completed sections. What is the most likely cause?
mediumWhat is the primary purpose of a vapor retarder in a commercial roofing system?
easyIn wood frame construction, what is the standard spacing for wall studs in commercial construction?
easyDuring site grading operations, the contractor discovers unsuitable soil conditions 3 feet below the planned foundation elevation. The soil exhibits high plasticity and poor drainage characteristics. What is the most appropriate immediate action?
mediumWhat is the primary purpose of using geotextile fabric in earthwork applications?
easyWhen installing engineered roof trusses, what is the most critical factor to verify before placement?
mediumA structural steel beam connection requires 6 high-strength bolts in a double-shear configuration. Each bolt has a shear capacity of 15 kips per shear plane. What is the total shear capacity of the connection?
mediumA W12×50 beam connection requires 6 high-strength bolts in double shear. Each bolt has a shear capacity of 21.6 kips per shear plane. What is the total shear capacity of the connection?
mediumA cut and fill operation requires moving 2,500 cubic yards of soil. The soil has a swell factor of 25% and a shrinkage factor of 8%. How many cubic yards must be excavated to achieve 2,500 cubic yards of compacted fill?
mediumAn 8-inch CMU wall is being constructed in an area with high wind loads. The engineer specifies grouted cells at 32 inches on center with #5 rebar. What is the primary purpose of this reinforcement?
medium+ 41 more questions
Other Exam Parts
Business & Financial Management
120Q · 6 content areas
Contract Administration
60Q · 4 content areas
Project Management
60Q · 3 content areas
California Contractor License Exam
150Q · 5 content areas
Georgia Contractor Supplement Exam
50Q · 1 content areas
North Carolina Contractor Supplement Exam
50Q · 1 content areas
About NASCLA Commercial General Building Contractor
125
Scored Questions
5.0h
Time Limit
2.4m
Per Question
The NASCLA Commercial General Building Contractor exam is administered by Pearson VUE. You must score at least 70% to pass this part. The exam is open book — you may bring up to 15 approved reference materials into the testing center, but with only 2.4 minutes per question, efficient tab-marking and familiarity with your references are essential.
The nationally recognized exam for commercial general building contractors, accepted by 15+ states. Covers project management, estimating, safety, contracts, financial management, and construction methods.
What's Tested: 7 Content Areas
22%
Project Management
Project scheduling (CPM, Gantt), resource allocation, subcontractor coordination, quality control, and project closeout.
~25 questions on the exam
18%
Estimating
Quantity takeoff, material/labor/equipment cost estimation, overhead & profit, bid preparation.
~21 questions on the exam
15%
Safety & OSHA
OSHA 29 CFR 1926, fall protection, excavation safety, scaffolding, hazard communication, PPE, confined space.
~17 questions on the exam
15%
Contract Law & Documents
Contract types, AIA documents, change orders, payment applications, bonds, dispute resolution.
~17 questions on the exam
15%
Financial Management
Job cost accounting, cash flow, financial statements, payroll, taxes, depreciation, insurance.
~17 questions on the exam
10%
Plans, Specs & Codes
Drawing interpretation, CSI MasterFormat, IBC building codes, ADA, shop drawings and submittals.
~12 questions on the exam
5%
Construction Methods & Materials
Concrete, masonry, structural steel, wood framing, roofing, earthwork.
~6 questions on the exam
Prioritize by Weight
Focus on Project Mgmt (22%) and Estimating (18%) first — they cover the most questions.
Tab Your References
With only 2.4 min/question, you need to find answers fast. Color-code tabs by content area.
Master the Math
Calculation questions (payroll, overhead, bidding) are common. Practice with our math calculator until the formulas are second nature.
Know Your Statutes
State-specific laws and regulations are heavily tested. Bookmark these sections in your reference books for quick lookup.
Simulate Exam Conditions
Take timed 125-question practice sessions to build stamina for the 5.0-hour exam.
Review Wrong Answers
Use the wrong book feature to revisit missed questions. Understanding why an answer is wrong is as important as knowing the right answer.
Frequently Asked Questions
How many questions are on the NASCLA Commercial General Building Contractor exam?
The NASCLA Commercial General Building Contractor exam contains 125 scored questions. You must answer them within 5.0 hours. The exam is administered by Pearson VUE and is open book — you may bring approved reference materials.
What is the passing score for NASCLA?
You need a score of 70% or higher to pass the NASCLA Commercial General Building Contractor exam. That means you must answer at least 88 out of 125 questions correctly.
Is the NASCLA exam open book?
Yes. The NASCLA contractor exam is open book. You are allowed to bring approved reference books into the testing center. However, time management is critical — you cannot look up every answer.
How long do I have to complete the NASCLA exam?
You have 5.0 hours (300 minutes) to complete all 125 questions. That averages to about 2.4 minutes per question.
Master NASCLA
Practice all 500 questions interactively with progress tracking and adaptive difficulty.
Start Free Practice