A pay application includes materials stored off site. What documentation is normally needed before payment is considered?
Correct Answer
A) Evidence required by the contract, such as invoices, insurance, storage location, and owner interest in the stored materials
Payment for stored materials normally requires supporting documentation such as invoices, storage and insurance evidence, and proof the materials are reserved for the project. Other choices lack the controls needed before payment.
Why This Is the Correct Answer
Payment for stored materials normally requires supporting documentation such as invoices, storage and insurance evidence, and proof the materials are reserved for the project. Other choices lack the controls needed before payment.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
