A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
Correct Answer
A) 347 cy
Each side widens 1.5 x 6 = 9 ft, so top width is 4 + 18 = 22 ft. Average width is (4 + 22)/2 = 13 ft. Volume is 120 x 13 x 6 = 9,360 cf, and 9,360/27 = 346.7 cy, or about 347 cy. Other choices use the bottom width only, one side slope only, or a 1H:1V slope.
Why This Is the Correct Answer
Each side widens 1.5 x 6 = 9 ft, so top width is 4 + 18 = 22 ft. Average width is (4 + 22)/2 = 13 ft. Volume is 120 x 13 x 6 = 9,360 cf, and 9,360/27 = 346.7 cy, or about 347 cy. Other choices use the bottom width only, one side slope only, or a 1H:1V slope.
Why the Other Options Are Wrong
Option B: 267 cy
sloped excavation volume, choice a: 267 cy implies about 222.5 percent fall over 120 ft; the stated slope is the one used in.
Option C: 293 cy
sloped excavation volume, choice b: 293 cy is wrong because 293 cy implies about 244.17 percent fall over 120 ft; the stated slope is the one used in.
Option D: 320 cy
sloped excavation volume, choice c: 320 cy implies about 266.67 percent fall over 120 ft; the stated slope is the one used in.
Memory Technique
Remember sloped excavation volume as "base, adjustment, final unit"; the last unit should read 347 cy.
Reference Hint
Open 29 CFR Part 1926, Subpart P - Excavations; use 29 CFR 1926 Subpart P Appendix B, Table B-1; excavation volume calculation to confirm that Each side widens 1.5 x 6 = 9 ft, so top width is 4 + 18 = 22 ft.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
Nineteen steel deck sheets each cover 31 sq ft. What total coverage is available before waste?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
