An EIFS wall terminates above finished earth at the base of a building. What minimum clearance is commonly required by ANSI/EIMA installation practice at grade?
Correct Answer
D) 6 in.
ANSI/EIMA EIFS installation practice commonly requires EIFS to terminate at least 6 in. above finished grade to reduce moisture exposure and impact at the base. Other choices are typical clearances at some paved or roof conditions, or an excessive nonstandard value.
Why This Is the Correct Answer
ANSI/EIMA EIFS installation practice commonly requires EIFS to terminate at least 6 in. above finished grade to reduce moisture exposure and impact at the base. Other choices are typical clearances at some paved or roof conditions, or an excessive nonstandard value.
Why the Other Options Are Wrong
Option A: 2 in.
In thermal and moisture protection, 2 in. is the wrong selection for EIFS clearance: 2 in. is a different published number than the cited EIFS clearance value; ANSI/EIMA 99-A-2017 EIFS termination clearances supports 6 in.
Option B: 4 in.
The trap in B is 4 in. That selection is wrong because 4 in. is a different published number than the cited EIFS clearance value; ANSI/EIMA 99-A-2017 EIFS termination clearances supports 6 in.; EIFS commonly terminates at least 6 in.
Option C: 12 in.
Choice C gives 12 in. Its specific error: 12 in. is a different published number than the cited EIFS clearance value; ANSI/EIMA 99-A-2017 EIFS termination clearances supports 6 in. The accepted answer is 6 in.
Memory Technique
Make EIFS clearance a tabbed card: cite the exact condition, then choose 6 in.
Reference Hint
Open ANSI/EIMA 99-A-2017, Exterior Insulation and Finish Systems; use the index entry or section for "ANSI/EIMA 99-A-2017 EIFS termination clearances" to confirm that ANSI/EIMA EIFS installation practice commonly requires EIFS to terminate at least 6 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
Next Question
A rooftop unit motor has a running amp value on the equipment submittal and a much higher starting demand. What should the GC coordinate before rough-in?
