A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
Correct Answer
B) 19.6 cy
Bedding volume is 240 x 4 x 0.5 = 480 cf. 480/27 = 17.8 cy; adding 10 percent gives 17.8 x 1.10 = 19.6 cy. Other choices omit the allowance, add too much allowance, or treat 6 in. as 0.6 ft.
Why This Is the Correct Answer
Bedding volume is 240 x 4 x 0.5 = 480 cf. 480/27 = 17.8 cy; adding 10 percent gives 17.8 x 1.10 = 19.6 cy. Other choices omit the allowance, add too much allowance, or treat 6 in. as 0.6 ft.
Why the Other Options Are Wrong
Option A: 17.8 cy
pipe bedding volume, choice b: the answer choice lifts 17.8 cy from the working line 480/27 = 17.8 cy.
Option C: 21.4 cy
pipe bedding volume, choice c: 21.4 cy equals about 577.8 cf after cubic-yard conversion; the accepted cubic-foot volume is 480 cf before dividing by 27 in.
Option D: 24.0 cy
pipe bedding volume, choice d: 24.0 cy is wrong because 24.0 cy equals about 648 cf after cubic-yard conversion; the accepted cubic-foot volume is 480 cf before dividing by 27 in.
Memory Technique
Keep a ledger line beside pipe bedding volume: if one number is skipped, the option drifts away from 19.6 cy.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use the index entry or section for "Pipe bedding aggregate quantity takeoff" to confirm that Bedding volume is 240 x 4 x 0.5 = 480 cf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
Nineteen steel deck sheets each cover 31 sq ft. What total coverage is available before waste?