Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Correct Answer
C) It protects the owner if the bidder refuses to enter the contract or furnish required bonds
Bid security protects the owner if a successful bidder fails to execute the contract or provide required bonds. Other choices confuse bid security with payment processing, post-award bonding, or change authorization.
Why This Is the Correct Answer
Bid security protects the owner if a successful bidder fails to execute the contract or provide required bonds. Other choices confuse bid security with payment processing, post-award bonding, or change authorization.
Why the Other Options Are Wrong
Option A: Use bid security to pay monthly subcontractor invoices
Choice A gives It pays monthly subcontractor invoices. Its specific error: it shifts the question into contract administration money flow.
Option B: Use bid security to replace the performance bond after award
Choice B (It replaces the performance bond after award) is rejected because it treats Bid security as optional.
Option D: Use bid security to authorize field changes without owner approval
The trap in D is It authorizes field changes without owner approval. That selection is wrong because the action skips the timing, documentation, or field-control step needed for Bid security.
Memory Technique
File bid security under a badge: condition first, number or duty second, answer It protects the owner if the bidder refuses to enter the contract or furnish required bonds.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Bid security and bid bond requirements" to confirm that Bid security protects the owner if a successful bidder fails to execute the contract or provide required bonds.
More NASCLA Questions
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
Nineteen steel deck sheets each cover 31 sq ft. What total coverage is available before waste?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During turnover, a panel directory still lists several breakers as spare even though they feed occupied tenant circuits. What is the best closeout correction?
Next Question
A contractor had 3 OSHA-recordable cases and 150,000 labor-hours. What is the total recordable incident rate using the 200,000-hour base?
