A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Correct Answer
D) 754 lf
Linear footage before allowance is 320 x 12 / 5.5 = 698.2 lf. Adding 8 percent gives 698.2 x 1.08 = 754.1 lf, or about 754 lf. Other choices omit the allowance, use a 6 in. face width, or add too much material.
Why This Is the Correct Answer
Linear footage before allowance is 320 x 12 / 5.5 = 698.2 lf. Adding 8 percent gives 698.2 x 1.08 = 754.1 lf, or about 754 lf. Other choices omit the allowance, use a 6 in. face width, or add too much material.
Why the Other Options Are Wrong
Option A: 699 lf
decking linear footage, choice a: 699 lf is wrong because 699 lf is the base quantity before the 8 percent add-on; the accepted calculation applies that add-on in.
Option B: 732 lf
decking linear footage, choice b: 732 lf implies about 4.84 percent added to 698.2; the stated add-on is 8 percent in.
Option C: 812 lf
decking linear footage, choice d: 812 lf is wrong because 812 lf implies about 16.3 percent added to 698.2; the stated add-on is 8 percent in.
Memory Technique
Keep a label beside decking linear footage: if one number is skipped, the option drifts away from 754 lf.
Reference Hint
Open Carpentry and Building Construction, 2016; use the index entry or section for "Deck board quantity by actual board face width" to confirm that Linear footage before allowance is 320 x 12 / 5.5 = 698.2 lf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
Nineteen steel deck sheets each cover 31 sq ft. What total coverage is available before waste?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Roof trusses have been set, but the required temporary restraint and diagonal bracing are incomplete. A roofing supplier wants to land bundles on the trusses. What should happen?
Next Question
During turnover, a panel directory still lists several breakers as spare even though they feed occupied tenant circuits. What is the best closeout correction?