During turnover, a panel directory still lists several breakers as spare even though they feed occupied tenant circuits. What is the best closeout correction?
Correct Answer
C) Update the circuit directory so each circuit is legibly identified
Panel directories should accurately and legibly identify circuit purposes so circuits can be operated and serviced. Other choices defer tracing or leave occupants and maintenance staff without usable circuit identification.
Why This Is the Correct Answer
Panel directories should accurately and legibly identify circuit purposes so circuits can be operated and serviced. Other choices defer tracing or leave occupants and maintenance staff without usable circuit identification.
Why the Other Options Are Wrong
Option A: The coordinator should leave the directory blank to avoid later changes
A blank directory leaves maintenance staff unable to identify which breaker controls each occupied tenant circuit.
Option B: Tell maintenance to trace circuits after occupancy
Tracing after occupancy shifts a closeout defect to the owner and can make routine service or emergency shutdown slower.
Option D: Number only the three largest breakers and use that item to close panel directory
Only labeling the largest breakers leaves smaller tenant circuits unidentified, which defeats the purpose of the directory.
Memory Technique
Remember panel directory by its jobsite consequence: the correct move points to Update the circuit directory so each circuit is legibly identified.
Reference Hint
Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use by topic index - electrical working space / panelboards to confirm that Panel directories should accurately and legibly identify circuit purposes so circuits can be operated and serviced.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Next Question
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?