Using 1 refrigeration ton = 12,000 Btu/h, how many tons of cooling correspond to a scheduled capacity of 180,000 Btu/h?

Correct Answer

D) 15 tons

180,000 Btu/h ÷ 12,000 Btu/h per refrigeration ton = 15 tons of cooling. This is a heat-removal rate, not equipment weight or a complete sizing calculation.

Answer Options
A
12 tons
B
18 tons
C
20 tons
D
15 tons

Why This Is the Correct Answer

180,000 Btu/h ÷ 12,000 Btu/h per refrigeration ton = 15 tons of cooling. This is a heat-removal rate, not equipment weight or a complete sizing calculation.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.