Resilient flooring is scheduled over a new concrete slab, but moisture testing has not been completed. The flooring crew wants to install to meet the turnover date. What is the correct field decision?
Correct Answer
D) Complete required slab moisture and pH tests and follow the flooring manufacturer's limits before installation
Resilient flooring failures often come from slab moisture or alkalinity outside manufacturer limits; required testing should be completed before adhesive installation. Other choices risk bond failure and warranty rejection.
Why This Is the Correct Answer
Resilient flooring failures often come from slab moisture or alkalinity outside manufacturer limits; required testing should be completed before adhesive installation. Other choices risk bond failure and warranty rejection.
Why the Other Options Are Wrong
Option A: The crew should install and rely on the adhesive warranty, leaving floor moisture testing unverified
Choice A (Install and rely on the adhesive warranty) is rejected because it answers the Floor moisture testing prompt with the wrong practical move.
Option B: The crew should install only in low-traffic rooms and leave floor moisture testing unchecked
In finishes, Install only in low-traffic rooms is the wrong selection for Floor moisture testing: it tries to bypass the Floor moisture testing checkpoint.
Option C: Add more adhesive to overcome moisture, leaving floor moisture testing unverified
The trap in C is Add more adhesive to overcome moisture. That selection is wrong because the choice would not get the project to Complete required slab moisture and pH tests and follow the flooring manufacturer's limits before.
Memory Technique
Use the phrase "problem, control, result" for floor moisture testing; the result side is Complete required slab moisture and pH tests and follow the flooring manufacturer's limits before installation.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Resilient flooring substrate moisture testing" to confirm that Resilient flooring failures often come from slab moisture or alkalinity outside manufacturer limits; required testing should be completed before adhesive installation.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
