Contract Administration
Cost estimation, project contracts, licensing/permits, and construction procedures for Florida contractors.
Content Areas
Preconstruction Activities
Cost estimates (material/labor/equipment), bid evaluation, square-foot estimating, contingency.
190Q available · 27% weight
Project Contracts
Contract types (lump sum/cost-plus/GMP/unit price), subcontracting, change orders, liens, closeout.
280Q available · 40% weight
Obtaining Licenses, Permits and Approvals
License types (Ch.489 F.S.), building permits, inspection scheduling.
140Q available · 20% weight
Construction Procedures and Operations
CPM scheduling, construction coordination, safety meetings, LEED/sustainability.
90Q available · 13% weight
Practice Questions
Preconstruction Activities
190QAn addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
mediumA slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
mediumAn addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
mediumA CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
mediumAn office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
mediumA framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
mediumA scope is expected to cost $420,000. The contractor wants a 16% margin on selling price. What selling price is required?
mediumProject general conditions are estimated at $73,500 for a 14-week project. If the owner asks for the weekly cost, what amount is it?
mediumBank excavation is 1,850 cy. If material swells 18% when hauled loose, how many loose cubic yards will be hauled?
mediumA pad requires 2,640 cy of compacted fill in place. Borrow material yields 90% after compaction. How many loose cubic yards should be ordered?
mediumA vinyl flooring takeoff is 6,875 sf. The estimator carries 5.5% waste. What quantity should be priced?
mediumA bid carries 68 cy of flowable fill at $154 per cy plus a $900 setup charge. What total should be included?
mediumA monthly payment application requests $186,000 of earned work. If retainage is 5%, what net payment should be forecast before other deductions?
mediumA steel quote is $142,000 and the estimator carries a 4% escalation allowance before award. What amount should be carried for steel?
mediumTaxable material totals $218,400 and applicable tax is estimated at 7%. What tax amount should be included?
mediumA crane has 3 standby days at $1,950 per day after a delivery delay. If a change estimate includes those standby days only, what amount is requested?
mediumAlternate A adds $28,500 of scope and deletes $6,200 of base scope. With 10% overhead and profit on the net add, what additive alternate should be listed?
mediumA conceptual storage building is 22,600 sf at a benchmark of $148 per sf. What budget does that produce?
mediumTemporary power is estimated at $1,180 per month for 7 months plus a $2,400 hookup charge. What amount should be carried?
mediumDemolition debris is estimated at 42 tons. Hauling and disposal cost is $96 per ton plus $750 for containers. What total should be carried?
mediumA night-shift labor line would normally be $36,000, but the estimate carries a 12% productivity premium. What labor amount should be included?
mediumA permit fee allowance is estimated at 1.1% of a $1,940,000 construction value. What allowance should be carried?
mediumA long-lead equipment vendor requires a 30% deposit on a $74,000 package. What cash requirement should be forecast?
mediumA bid review finds a $12,500 unresolved scope gap and management carries a 15% risk factor on that gap. What risk amount is added?
mediumA slab package requires vapor barrier under 18,900 sf of slab. The estimator carries 8% lap and waste. What square footage should be priced?
mediumA continuous footing is 420 lf long, 30 in wide, and 12 in deep. Including 5% waste, how many cubic yards of concrete should be carried?
mediumA low-slope roof takeoff is 31,760 sf. If the estimator prices roofing by the square and carries 4% waste, how many squares should be included?
mediumInterior wall paint covers 365 sf per gallon. The net painted wall area is 14,235 sf and one coat is required. How many gallons should be estimated before tint overage?
mediumA restroom floor takeoff is 1,920 sf. Tile cartons cover 16 sf each, and the estimate carries 7% waste. How many cartons should be ordered?
mediumPartition surfaces total 18,480 sf. Standard boards cover 32 sf, and the estimator carries 9% waste. How many boards should be included?
medium+ 160 more questions
Project Contracts
280QAn owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
mediumThe GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
mediumThe architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
mediumA subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
mediumA Florida GC finds a conflict between a plan note and the specifications during buyout. Under AIA A201, what should the GC do with the Contract Documents?
mediumOwner and contractor agree on added work, price, and time. Which AIA A201 instrument should document it?
mediumThe owner cancels remaining work for business reasons unrelated to contractor default. Which AIA A201 provision controls?
mediumThe drawings show a finish detail that is not repeated in every room schedule. Under AIA A201 correlation principles, how should the GC approach the documents?
mediumA GC needs evidence that the Florida owner can fund the Work before continuing after contract execution. Which AIA A201 topic controls that request?
mediumThe owner wants to provide surveys and legal descriptions needed for the Work. Under AIA A201, where is this owner-side responsibility addressed?
mediumA Florida owner asks the architect to direct exactly how the GC's crew should brace temporary work. Under AIA A201, which party is generally responsible for construction means and methods?
mediumA substitution would lower material cost but does not meet the specified performance. What AIA A201 contractor duty is implicated?
mediumAfter installation, a finish product fails because it does not conform to the Contract Documents. Which AIA A201 contractor obligation is most directly involved?
mediumA Florida bid recap must account for taxes legally enacted when bids are received. Under AIA A201, who normally pays sales, consumer, use, and similar taxes for the Work?
mediumUnless the Contract Documents provide otherwise, a Florida GC must obtain permits and inspections customarily required after contract execution. Which AIA A201 topic controls this?
mediumDuring demolition, the GC discovers concealed conditions materially different from those indicated in the Contract Documents. What AIA A201 action should follow?
mediumThe specifications include a fixture allowance because final selections are pending. How should allowance work be administered under AIA A201?
mediumThe owner wants a single field representative from the GC for daily jobsite communication. Under AIA A201, which role fits?
mediumSoon after award, the owner requests the GC's plan for sequencing the Work. Which AIA A201 contractor duty is triggered?
mediumA long-lead storefront package must be reviewed early. Under AIA A201, what schedule helps coordinate that review?
mediumThe owner asks why the GC keeps updated contract documents and change documents at the jobsite. Which AIA A201 duty explains this?
mediumA shop drawing shows how the subcontractor proposes to fabricate a component. Under AIA A201, what does architect review generally mean?
mediumA subcontractor needs to cut existing finished work to install new piping. Under AIA A201, which topic governs the GC's coordination responsibility?
mediumThe owner complains that construction waste is accumulating in occupied adjacent space. Which AIA A201 contractor duty applies?
mediumThe GC receives a payment certificate from the architect. Under AIA A201, which general role is the architect performing?
mediumThe parties disagree about a drawing requirement and ask for interpretation. Under AIA A201, which role commonly interprets and decides matters concerning performance?
mediumThe owner has a reasonable objection to a proposed subcontractor before award of that subcontract. Under AIA A201, what should the GC recognize?
mediumA subcontractor damages adjacent work while performing its trade scope. Under AIA A201, how does subcontracting affect the GC's responsibility?
mediumThe owner contracts separately for low-voltage work on the same Florida project. What should the GC expect under AIA A201 coordination concepts?
mediumThe owner and GC agree on a revised storefront detail, a $18,000 increase, and no time change. Which AIA A201 instrument should record the agreement?
medium+ 250 more questions
Obtaining Licenses, Permits and Approvals
140QA local office tells an applicant that recording a notice of commencement is a condition to processing the building permit application. What should the GC check?
mediumA Florida notice of commencement is recorded for a project. When is the giving of the notice generally effective under Chapter 713?
mediumWho must sign the notice of commencement under Florida lien-law requirements?
mediumIf a qualifying agent ceases to be affiliated with a business organization, what Florida licensing issue is triggered?
mediumFlorida authorities find probable cause that regulated contracting work is being performed without a current valid certificate or registration. What enforcement tool may apply?
mediumA certified contractor commits a licensing violation. Which Florida source describes board discipline such as probation, fines, suspension, or revocation?
mediumThe approved permit drawings conflict with a later shop drawing. What should the GC do before installing the changed work?
mediumA required inspection is needed before concrete placement. What should the superintendent do?
mediumThe tenant wants to use the space after final inspection corrections are complete. Which approval should the GC confirm before occupancy when required?
mediumA site needs temporary electrical service before the full notice-of-commencement package is provided. Which Chapter 713 issue should be checked?
mediumThe contract is silent and the permit fee is customarily required for the contractor's execution of the work. What should the GC expect administratively?
mediumThe building department returns plan review comments before permit issuance. What should the GC coordinate?
mediumA local jurisdiction identifies administrative requirements in addition to the base Florida Building Code. What should the GC do?
mediumA contract and permit application list different contracting business names for the same work. What is the licensing concern?
mediumA permit inspection passes with correction notes for follow-up documentation. What should the GC retain?
mediumA plumbing subpermit is not final, but the GC wants the overall final inspection. What should the PM verify?
mediumA qualifier is listed for a contracting business but is not exercising required responsibility over the work. What source controls that risk?
mediumWork stops for an extended period and the permit may expire under local administration rules. What should the GC do?
mediumThe permit documents call for inspection reports from an approved inspection agency. What is the GC's administrative duty?
mediumA notice must be served using project information. Which reference helps determine service addresses tied to the notice of commencement or permit application?
mediumA direct contract exceeds $5,000 and the first inspection is approaching. What must be filed with the issuing authority before that inspection can be approved?
mediumThe notice of commencement lists a different contractor name than the permit application. What administrative issue should be corrected?
mediumA local government issues a separate temporary electrical service permit before the main improvement notice paperwork is complete. What is the lien-law point to verify?
mediumA notice of commencement was recorded, but no work actually starts for more than 90 days. What should the PM verify before relying on it?
mediumThe owner changes contractors after a notice of commencement has been recorded. Which notice issue should be checked?
mediumAn owner wants to terminate the effective period of a notice of commencement. What documentation issue must be addressed?
mediumA tenant wants to start demolition before the permit is issued because the work is inside the existing space. What is the code-administration answer?
mediumThe permit drawings and a later field sketch disagree on a rated wall detail. What should the GC do before building the changed detail?
mediumA required above-ceiling inspection is scheduled, but ceiling tile installation would conceal the work. What should the superintendent do?
mediumThe owner wants employees to move into the space after final cleaning but before occupancy approval. What should the GC confirm?
medium+ 110 more questions
Construction Procedures and Operations
90QA weekly coordination meeting resolves a sequencing issue that affects three trades. What should the PM do after the meeting?
mediumThe architect returns a reviewed submittal with comments that affect installation. What should the GC do?
mediumA delivery arrives with damaged packaging and missing certification documents. What should the superintendent do?
mediumA two-week look-ahead schedule shows drywall starting before rough inspections. What should the superintendent do?
mediumThe owner verbally asks for a small added task during a site walk. What is the best field-administration response before doing the work?
mediumA pipe route changes in the field with approved direction. What should the GC do with record documents?
mediumThe architect rejects a portion of installed finish work. What field-control action helps manage correction?
mediumA trade plans hot work in an occupied renovation area. What should the GC coordinate operationally?
mediumRoofing material will arrive before the deck is ready and storage space is limited. What should the PM do?
mediumThe owner asks how warranties, O&M manuals, attic stock, and training will be tracked. What should the PM use?
mediumA required pressure test fails. What should the superintendent do next?
mediumA mechanical system requires startup and commissioning support before turnover. What should the GC coordinate?
mediumA trade falls behind because it is not staffing the work as planned. What is the best operational response?
mediumA rain event stops exterior work and affects two subcontractors. What should the superintendent document that day?
mediumA field dimension conflicts with a drawing note, and the answer affects fabrication. What should the PM do?
mediumA submittal is returned 'revise and resubmit' with comments affecting product selection. What should the GC do?
mediumMoisture-sensitive flooring arrives three weeks early during humid weather. What field operation is best?
mediumA crew will install edge metal near an unprotected roof edge. What should the GC coordinate before work begins?
mediumA slab pour is scheduled for tomorrow. Reinforcing, embeds, vapor barrier, and inspection status are not fully confirmed. What should the superintendent do?
mediumSeveral owner-directed changes are authorized at different stages. What record helps the PM manage pricing and approval status?
mediumA two-week look-ahead shows tile starting before substrate moisture testing and HVAC conditioning. What should the superintendent do?
mediumThe architect issues punch-list items assigned to three trades. What is the best control for the GC?
mediumThe specifications require owner training for mechanical controls before turnover. What should the PM coordinate?
mediumA tropical storm watch is issued while exterior openings are incomplete. What operational response should the GC coordinate?
mediumA revised drawing changes a ceiling access-panel location after older sheets were already distributed. What should the PM do?
mediumA subcontractor repeatedly misses agreed recovery dates after written coordination efforts. What should the PM do next?
mediumA Florida superintendent receives a revised approved detail. What field procedure should follow?
mediumBefore mobilization, the GC schedules a meeting with major subcontractors. What is the main operational value of that meeting?
mediumElectrical rough-in will conflict with fire-sprinkler mains unless the trades coordinate above the corridor ceiling. What should the GC do?
mediumA field question may affect layout and cost. What should the project manager use to keep the issue controlled?
medium+ 60 more questions
Other Exam Parts
Business & Financial Management
120Q · 6 content areas
Project Management
60Q · 3 content areas
NASCLA Commercial General Building Contractor
125Q · 12 content areas
California Law & Business
115Q · 7 content areas
California Class B Trade
115Q · 5 content areas
California Contractor License Exam
150Q · 5 content areas
About Contract Administration
60
Scored Questions
4.5h
Time Limit
4.5m
Per Question
The Contract Administration exam is administered by Pearson VUE. You must score at least 70% to pass this part. The exam is open book — you may bring approved reference materials into the testing center, but with only 4.5 minutes per question, efficient tab-marking and familiarity with your references are essential.
Cost estimation, project contracts, licensing/permits, and construction procedures for Florida contractors.
What's Tested: 4 Content Areas
40%
Project Contracts
Contract types (lump sum/cost-plus/GMP/unit price), subcontracting, change orders, liens, closeout.
~24 questions on the exam
27%
Preconstruction Activities
Cost estimates (material/labor/equipment), bid evaluation, square-foot estimating, contingency.
~16 questions on the exam
20%
Obtaining Licenses, Permits and Approvals
License types (Ch.489 F.S.), building permits, inspection scheduling.
~12 questions on the exam
13%
Construction Procedures and Operations
CPM scheduling, construction coordination, safety meetings, LEED/sustainability.
~8 questions on the exam
Prioritize by Weight
Focus on Contracts (40%) and Preconstruction (27%) first — they cover the most questions.
Tab Your References
With only 4.5 min/question, you need to find answers fast. Color-code tabs by content area.
Master the Math
Calculation questions (payroll, overhead, bidding) are common. Practice with our math calculator until the formulas are second nature.
Know Your Statutes
State-specific laws and regulations are heavily tested. Bookmark these sections in your reference books for quick lookup.
Simulate Exam Conditions
Take timed 60-question practice sessions to build stamina for the 4.5-hour exam.
Review Wrong Answers
Use the wrong book feature to revisit missed questions. Understanding why an answer is wrong is as important as knowing the right answer.
Frequently Asked Questions
How many questions are on the Contract Administration exam?
The Contract Administration exam contains 60 scored questions. You must answer them within 4.5 hours. The exam is administered by Pearson VUE and is open book — you may bring approved reference materials.
What is the passing score for Contract Admin?
You need a score of 70% or higher to pass the Contract Administration exam. That means you must answer at least 42 out of 60 questions correctly.
Is the Contract Admin exam open book?
Yes. The Contract Admin contractor exam is open book. You are allowed to bring approved reference books into the testing center. However, time management is critical — you cannot look up every answer.
How long do I have to complete the Contract Admin exam?
You have 4.5 hours (270 minutes) to complete all 60 questions. That averages to about 4.5 minutes per question.
Master Contract Admin
Practice all 700 questions interactively with progress tracking and adaptive difficulty.
Start Free Practice