EstatePass
Contract AdminPermitsmedium20% of exam part

A local government issues a separate temporary electrical service permit before the main improvement notice paperwork is complete. What is the lien-law point to verify?

Correct Answer

B) Apply the temporary-utility exception but protect the main inspection requirement

Florida law allows limited preliminary permits or inspections without treating them as the main notice trigger.

Answer Options
A
Temporary service cancels every later notice-of-commencement obligation for the improvement
B
Apply the temporary-utility exception but protect the main inspection requirement
C
The electrical subcontractor becomes the owner for all recorded lien-law documents
D
The permit fee receipt replaces all building-code inspection approvals

Why This Is the Correct Answer

Florida law allows limited preliminary permits or inspections without treating them as the main notice trigger.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.