A local government issues a separate temporary electrical service permit before the main improvement notice paperwork is complete. What is the lien-law point to verify?
Correct Answer
B) Apply the temporary-utility exception but protect the main inspection requirement
Florida law allows limited preliminary permits or inspections without treating them as the main notice trigger.
Why This Is the Correct Answer
Florida law allows limited preliminary permits or inspections without treating them as the main notice trigger.
Why the Other Options Are Wrong
Option A: Temporary service cancels every later notice-of-commencement obligation for the improvement
Temporary service cancels every later notice-of-commencement obligation for the improvement may relate to another site control, but it does not remove or guard the temporary utility exception exposure being tested.
Option C: The electrical subcontractor becomes the owner for all recorded lien-law documents
The electrical subcontractor becomes the owner for all recorded lien-law documents may relate to another site control, but it does not remove or guard the temporary utility exception exposure being tested.
Option D: The permit fee receipt replaces all building-code inspection approvals
The permit fee receipt replaces all building-code inspection approvals may relate to another site control, but it does not remove or guard the temporary utility exception exposure being tested.
Memory Technique
Name the harm before the guard; temporary, service, cancels cannot stand in for Needs Temporary.
Reference Hint
Open-book path: tab Florida Statutes Chapter 713 to Section 713.135 temporary utility and preliminary site-work permits; confirm the required quantity, authority, timing, or record before selecting the answer.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
