The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
Correct Answer
C) The Architect provides interpretations and decisions consistent with the Contract Documents
A201 assigns the Architect interpretation and decision duties during contract administration.
Why This Is the Correct Answer
A201 assigns the Architect interpretation and decision duties during contract administration.
Why the Other Options Are Wrong
Option A: The lowest bidder decides because its price was used at award, and treat the project meeting agenda as the contract instrument
The lowest bidder decides because its price was used at award, and treat the project meeting agenda as the contract instrument skips the written authority, scope, price, notice, or release control needed for architect interpretations.
Option B: The county inspector resolves every payment and contract dispute, and use that shortcut to decide the decisions interpretations provides requirement, without separating final completion from substantial completion
The county inspector resolves every payment and contract dispute, and use that shortcut to decide the decisions interpretations provides requirement, without separating final completion from substantial completion skips the written authority, scope, price, notice, or release control needed for architect interpretations.
Option D: The supplier whose product is affected issues a binding decision
The supplier whose product is affected issues a binding decision skips the written authority, scope, price, notice, or release control needed for architect interpretations.
Memory Technique
Architect square for Asks Interpretation: scope, authority, price, paper.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 4, Β§4.2 Interpretations and Decisions; match the contract role, notice step, and timing in the stem before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
A scope is expected to cost $420,000. The contractor wants a 16% margin on selling price. What selling price is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass