Debris is expected to require seven 30-cy pulls at $685 per pull plus $540 loading support. What cost should be carried?

Correct Answer

A) $5,335

Multiply pull count by unit price and add support cost.

Answer Options
A
$5,335
B
$4,795
C
$5,875
D
$6,020

Why This Is the Correct Answer

Multiply pull count by unit price and add support cost.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.