A project has been inactive long enough that the permit status is uncertain. What should the GC do before scheduling more inspections?

Correct Answer

B) Confirm permit status and obtain any needed extension or reactivation

Permit status and expiration are code-administration issues that must be verified with the authority having jurisdiction.

Answer Options
A
Assume the permit is active forever because a rough inspection passed months earlier
B
Confirm permit status and obtain any needed extension or reactivation
C
Ask the drywall subcontractor to approve continued inspections in the daily log
D
Wait until the owner occupies the space to decide whether the permit mattered

Why This Is the Correct Answer

Permit status and expiration are code-administration issues that must be verified with the authority having jurisdiction.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.