A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
Correct Answer
B) Subcontract Documents incorporating applicable prime contract and general-condition requirements
A401 defines the Subcontract Documents and connects the subcontract to applicable prime contract requirements.
Why This Is the Correct Answer
A401 defines the Subcontract Documents and connects the subcontract to applicable prime contract requirements.
Why the Other Options Are Wrong
Option A: Only the subcontractor's invoice form and internal cost report, and use that shortcut to decide the general prime requirement, and let the bidder list determine a construction-phase duty
Only the subcontractor's invoice form and internal cost report, and use that shortcut to decide the general prime requirement, and let the bidder list determine a construction-phase duty skips the written authority, scope, price, notice, or release control needed for subcontract documents.
Option C: Only the county inspection card and permit-routing receipt, while moving a construction claim into the permit file
Only the county inspection card and permit-routing receipt, while moving a construction claim into the permit file skips the written authority, scope, price, notice, or release control needed for subcontract documents.
Option D: Only the supplier quote attached to the subcontractor's bid
Only the supplier quote attached to the subcontractor's bid skips the written authority, scope, price, notice, or release control needed for subcontract documents.
Memory Technique
When defines clashes with connects, let the contract speak before Explains Flow-Down.
Reference Hint
Open-book path: tab AIA A401-2017 to Article 1, Subcontract Documents and relationship to A201/prime contract; match the contract role, notice step, and timing in the stem before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
A scope is expected to cost $420,000. The contractor wants a 16% margin on selling price. What selling price is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass