An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
Correct Answer
B) Site visits are part of contract administration and do not make the Architect responsible for means and methods
A201 describes the Architect's site visits without shifting contractor means-and-methods responsibility.
Why This Is the Correct Answer
A201 describes the Architect's site visits without shifting contractor means-and-methods responsibility.
Why the Other Options Are Wrong
Option A: Site visits transfer daily safety control to the Architect until final completion, and use that shortcut to decide the means requirement, and treat owner occupancy as acceptance of the procedure
Site visits transfer daily safety control to the Architect until final completion, and use that shortcut to decide the means requirement, and treat owner occupancy as acceptance of the procedure skips the written authority, scope, price, notice, or release control needed for architect site visits.
Option C: Site visits make the Owner responsible for all defective work discovered later
Site visits make the Owner responsible for all defective work discovered later skips the written authority, scope, price, notice, or release control needed for architect site visits.
Option D: Site visits replace the contractor's superintendent and site documents, while moving a construction claim into the permit file
Site visits replace the contractor's superintendent and site documents, while moving a construction claim into the permit file skips the written authority, scope, price, notice, or release control needed for architect site visits.
Memory Technique
Owner Questions shortcut is not a term until paper carries it.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 4, Β§4.2 Architect's Administration of the Contract; match the contract role, notice step, and timing in the stem before choosing.
More Contract Admin Questions
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
A scope is expected to cost $420,000. The contractor wants a 16% margin on selling price. What selling price is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
