A GC stores materials in an area the contract documents reserve for tenant access. Which AIA A201 topic should be checked?
Correct Answer
A) Contractor confinement of operations and use of site
A201 addresses how the Contractor confines operations to permitted areas and does not unreasonably encumber the site.
Why This Is the Correct Answer
A201 addresses how the Contractor confines operations to permitted areas and does not unreasonably encumber the site.
Why the Other Options Are Wrong
Option B: Final payment certification after closeout
Final payment certification after closeout skips the written authority, scope, price, notice, or release control needed for use of site.
Option C: Bid security replacement after award, and treating substantial completion as final completion
Bid security replacement after award, and treating substantial completion as final completion skips the written authority, scope, price, notice, or release control needed for use of site.
Option D: Owner's financial arrangements before bidding
Owner's financial arrangements before bidding skips the written authority, scope, price, notice, or release control needed for use of site.
Memory Technique
Contract square for Phased Renovation: scope, authority, price, paper.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 3, Section 3.13 Use of Site; compare the role, timing, and required instrument in the stem.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
After substantial completion, a door defect appears during the correction period. Which AIA A201 topic is most relevant?
Next Question
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?