The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
Correct Answer
D) The Architect may reject nonconforming Work as part of contract administration
A201 gives the Architect authority to reject Work that does not conform to the Contract Documents.
Why This Is the Correct Answer
A201 gives the Architect authority to reject Work that does not conform to the Contract Documents.
Why the Other Options Are Wrong
Option A: The Architect must accept the work if a subcontractor has already invoiced it
The Architect must accept the work if a subcontractor has already invoiced it skips the written authority, scope, price, notice, or release control needed for rejection of work.
Option B: The Owner's lender must decide whether the work is defective, and close the issue in the estimator's pricing notes
The Owner's lender must decide whether the work is defective, and close the issue in the estimator's pricing notes skips the written authority, scope, price, notice, or release control needed for rejection of work.
Option C: The low bidder from bid day has final authority over quality disputes, and use that shortcut to decide the architect requirement, and treat a subcontractor selection note as the owner's approval
The low bidder from bid day has final authority over quality disputes, and use that shortcut to decide the architect requirement, and treat a subcontractor selection note as the owner's approval skips the written authority, scope, price, notice, or release control needed for rejection of work.
Memory Technique
Rejection Of Work square for Has Finish: scope, authority, price, paper.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 4, Β§4.2 Rejection of Work; match the contract role, notice step, and timing in the stem before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
A scope is expected to cost $420,000. The contractor wants a 16% margin on selling price. What selling price is required?