Contract AdminPreconstructionmedium27% of exam part

A scope is expected to cost $420,000. The contractor wants a 16% margin on selling price. What selling price is required?

Correct Answer

A) $500,000

Margin is based on selling price, so divide cost by one minus the margin rate.

Answer Options
A
$500,000
B
$487,200
C
$493,600
D
$512,000

Why This Is the Correct Answer

Margin is based on selling price, so divide cost by one minus the margin rate.

Why the Other Options Are Wrong

Option B: $487,200

$487,200 is below the supported result for markup versus margin; it likely uses the wrong base, period, or account bucket.

Option C: $493,600

$493,600 is below the supported result for markup versus margin; it likely uses the wrong base, period, or account bucket.

Option D: $512,000

$512,000 is above the supported result for markup versus margin; it likely adds an unsupported amount or compares the wrong financial base.

Memory Technique

Markup Versus Margin fence: markup starts at cost, margin looks back from price.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Preconstruction estimating; margin on sales; match the role, timing, and required approval before choosing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.