EstatePass
All Parts60 Questions

Project Management

Construction methods, materials, safety, and blueprint reading for Florida contractors.

1120 questions available4.5 hours70% to pass
Difficulty Breakdown
Easy1 (0%)
Medium1097 (98%)
Hard22 (2%)

Practice Questions

E

Construction Methods, Materials, Tools & Equipment

880Q

Before the inspection hold point, the team confirms that the project condition shows that concealed service item needs access and rating continuity. Which access provision is appropriate?

medium

Before releasing the work, the team identifies this condition: the controlling field constraint is that frame must be mechanically anchored. Which opening anchorage fits best?

medium

At the hotel pool-equipment yard, during the next-week procurement cycle, a ride-on sweeper is needed for warehouse turnover cleaning for 14 days at $225 per day, plus a $145 delivery charge. What rental cost should be budgeted?

medium

During the next-week procurement cycle at the fire-station apparatus bay, the exposed beam run requires 176 LF of grade-beam forms at 2.5 ft high on 2 sides. What contact area is required?

medium

In the look-ahead meeting, the constraint is that long-lead item needs early coordinated release. Which procurement sequence should the project team carry?

medium

The work plan must account for this condition: predecessors must be ready. Which work-release condition is most suitable?

medium

The construction team is coordinating a method decision because accepted work still needs protection. Which closeout method is best?

medium

During the pre-installation review, the field issue is that the project condition shows that clean aggregate base must be densified efficiently. Which compaction equipment is the best match?

medium

A Florida superintendent must choose the proper material-handling equipment because the controlling field constraint is that material must be placed over an obstruction. Which option is best?

medium

The work plan must account for this condition: the controlling field constraint is that finishing should not trap bleed water. Which finishing decision is most suitable?

medium

For the upcoming operation, the key field fact is that the project condition shows that work is directly overhead on a flat slab. Which access equipment should govern the choice?

medium

The construction team is coordinating a method decision because the controlling field constraint is that vertical flashing needs secure termination. Which flashing detail is best?

medium

Before the inspection hold point, the team confirms that the project condition shows that granular backfill is in a narrow trench. Which compaction equipment is appropriate?

medium

The field condition is: the project condition shows that wood doors arrive before conditioning. Which storage method best matches the condition?

medium

On this project, the controlling condition is the project condition shows that the specification requires a mockup. Which quality-control step should be selected?

medium

In the look-ahead meeting, the constraint is that CMU units need accurate cuts. Which masonry tool should the project team carry?

medium

For the buyout verification pass at the school band-room storage, the partition run is 114 ft long and studs are placed at 12 ft on center, including one at the starting end. How many studs are needed?

medium

For the crew-release check at the airport service-court canopy, a isolated mat footing is 27 ft by 14 ft by 5 in. Including 8% waste, how many cubic yards of concrete are needed?

medium

For the field-takeoff reconciliation at the parking-garage stair tower, the exam-room perimeter requires 310 LF of rubber wall base plus 10% waste. Stock comes in 120 ft coils. How many coils are required?

medium

For the crew-release check at the cafeteria dishwashing alcove, the mezzanine edge is 234 ft long and posts are placed at 6 ft on center, including one at the starting end. How many posts are needed?

medium

For the next-week procurement cycle at the hotel pool-equipment yard, the adhesive-anchor order includes 192 cartridges at $31 each before a 18% contractor markup. What extended price should be carried?

medium

For the preconstruction estimate lock at the municipal pump-house slab, a sanitary pipe run has a 24 ft run at 1.00% slope. What invert drop is required in inches?

medium

For the field-takeoff reconciliation at the clubhouse cart-storage bay, the pavement area for asphalt patch fabric is 15570 SF and the order includes 7% waste. How many square yards are required?

medium

For the look-ahead planning meeting at the laboratory exhaust chase, the roof plane area for the shingle reroof totals 12880 SF. With 15% waste, how many roofing squares are needed?

medium

For the crew-release check at the county annex sally port, the slope-adjusted area for the metal roof panel order totals 11440 SF. With 15% waste, how many roofing squares are needed?

medium

For the field-takeoff reconciliation at the visitor-center exhibit wall, the canopy deck area for the canopy roof overlay totals 22600 SF. With 5% waste, how many roofing squares are needed?

medium

For the material-order review at the urgent-care ambulance canopy, a portable light tower is needed for night concrete pour for 16 days at $96 per day, plus a $310 delivery charge. What rental cost should be budgeted?

medium

During the crew-release check at the community-pool bathhouse, the partition side area for gypsum board layer is 5560 SF. With 12% waste and 32 SF per sheet or panel, how many sheets are required?

medium

During the crew-release check at the university bookstore shell, the deck screws scope includes 63 cement-board sheets, with 36 fasteners per item. Boxes contain 700 fasteners. How many boxes are needed?

medium

During the field-takeoff reconciliation at the athletic-locker shower bay, the masonry anchors scope includes 147 veneer tie locations, with 1 fasteners per item. Boxes contain 250 fasteners. How many boxes are needed?

medium

+ 850 more questions

F

Safety

120Q

A straight ladder at a Sanford job must reach 21 ft vertically. Using a 4-to-1 setup, about how far should the ladder base be from the wall?

medium

The West Palm Beach crane pick has this communication condition: operator cannot see the landing area. Which safety control should be used?

medium

The Daytona Beach job has this temporary-power condition: wet work area uses cord-connected equipment. Which safety control should the superintendent verify?

medium

A Daytona Beach crew will work at an unprotected roof edge 8 ft above the lower level. Which control should be in place before work begins?

medium

The Palm Coast job has this temporary-power condition: extension-cord circuit lacks protection. Which safety control should the superintendent verify?

medium

The West Palm Beach site has this scaffold workforce issue: crew member is assigned to erect scaffold components. Which record should the PM verify?

medium

A Sarasota trench will be 6 ft deep and employees must enter it. Which planning item is normally required unless the excavation is entirely in stable rock?

medium

A Cape Coral trench crew is placing excavated spoil beside the opening. What minimum distance from the edge should spoil and equipment be kept unless another protective method is used?

medium

A Deltona trench has a ladder 29 ft from the employee work location. What access status should be reported?

medium

A Clearwater trench has a ladder 41 ft from the employee work location. What access status should be reported?

medium

A Lakeland excavation has this condition before entry: rain occurred before the morning shift. Which safety step is required before work proceeds?

medium

The Boca Raton project has this exposure: worker enters an area with falling-object exposure. Which PPE action should be documented?

medium

Grinding metal creates flying-particle hazards to a worker’s eyes and face. Which PPE action addresses those hazards?

medium

A crew is about to use a solvent that introduces a chemical hazard for which the workers have not been trained. What should be completed before use?

medium

A Miramar worker finds an extension cord with this defect: outer jacket is cut. Which action is safest before use continues?

medium

The Bradenton project has this cutting/welding condition: welding continues after fire watch leaves. Which fire-prevention control should be documented?

medium

The Vero Beach site has this projection hazard: vertical reinforcing bars are exposed. Which safety control is needed?

medium

Debris blocks a required emergency-egress route in an occupied construction building. Which action restores that route?

medium

The Fort Myers work area has this housekeeping condition: scrap creates trip hazards near stairs. Which safety correction should be made?

medium

The Palm Bay work area has this housekeeping condition: nails remain in discarded lumber. Which safety correction should be made?

medium

Workers may enter a manhole with restricted access, but its hazards and permit-space status have not been evaluated. What must the employer arrange before work begins?

medium

The Deerfield Beach project has this stairway condition: temporary stairs lack handrail protection. Which safety control applies?

medium

The Eustis project has this stairway condition: stair landing is cluttered. Which safety control applies?

medium

Debris blocks a required emergency-egress route in an occupied construction building. Which action restores that route?

medium

A Tallahassee worker finds an extension cord with this defect: grounding prong is missing. Which action is safest before use continues?

medium

A site assessment identifies rigid exposed anchor rods as a recognized serious impalement hazard along a walkway. The approved control requires effective protective covers before reopening the walkway. Which action implements that control?

medium

The Deltona job has this respirable-dust condition: dry cutting concrete produces visible dust. Which safety control should be used?

medium

In a 6-foot-deep trench, the nearest safe egress from a worker’s location requires 36 feet of lateral travel. What correction is needed?

medium

A Eustis excavation has this condition before entry: vibration from nearby equipment increased. Which safety step is required before work proceeds?

medium

The Palm Bay job has this temporary-power condition: extension-cord circuit lacks protection. Which safety control should the superintendent verify?

medium

+ 90 more questions

G

Reading Plans and Specifications

120Q

From the room schedule, what area is listed for room 102?

medium

In the plumbing legend, what does symbol CO mean?

medium

In the electrical legend, what does symbol OS mean?

medium

From panel schedule H1, what wire size is listed for circuit H1-4?

medium

From the window schedule, what glass type is scheduled for W102?

medium

From panel schedule K, how many poles are listed for circuit K-5?

medium

In detail 9/A-404, what material is called out at keynote 16?

medium

From the grade beam takeoff plan, what concrete volume is required?

medium

On the partial floor plan, which room is directly south of the Electrical room?

medium

From the entry wall footing plan, what concrete volume should be ordered?

medium

From the door schedule, what size is listed for door D503?

medium

In detail 4/S-302, what note is listed for C2?

medium

From panel schedule L3, what breaker is assigned to circuit L3-5?

medium

In the site utility legend, what does symbol WM mean?

medium

From the dumpster pad plan, what perimeter length is needed for edge forming?

medium

From the monument sign footing plan, what concrete volume should be ordered?

medium

From the service pad plan, what perimeter length should be used?

medium

From the canopy footing takeoff plan, what concrete volume should be ordered for the continuous footing?

medium

From panel schedule P2, how many poles are listed for circuit P2-10?

medium

From the specialty equipment schedule, what anchor type is listed for SE-3?

medium

From the screen wall footing plan, what concrete volume is required?

medium

Using the drawing index, which sheet should you open for the plumbing fixture schedule?

medium

From the room schedule, what area is listed for room 601?

medium

From the light fixture schedule, what mount is listed for L1?

medium

In the rainscreen wall section, what material is keynote 23?

medium

From the bike storage slab plan, what slab area should be used for takeoff?

medium

From the generator pad plan, what perimeter length is needed for forms?

medium

Using the supplied practice drawing, in detail 7/A-403, what material is called out at keynote 11?

medium

From the life safety area schedule, what area is listed for Zone 4?

medium

Using the supplied practice drawing, from the finish schedule, what floor finish is shown for room 703?

medium

+ 90 more questions

About Project Management

60

Scored Questions

4.5h

Time Limit

4.5m

Per Question

The Project Management exam is administered by Pearson VUE. You must score at least 70% to pass this part. The exam is open book — you may bring approved reference materials into the testing center, but with only 4.5 minutes per question, efficient tab-marking and familiarity with your references are essential.

Construction methods, materials, safety, and blueprint reading for Florida contractors.

What's Tested: 3 Content Areas

E

63%

Construction Methods, Materials, Tools & Equipment

Site work, earthwork, concrete, masonry, wood framing, steel, innovative techniques (tilt-up/SIP/ICF), energy-efficient construction.

~38 questions on the exam

F

20%

Safety

OSHA standards (scaffolding/trenching/fall protection), asbestos/lead paint/hazardous waste.

~12 questions on the exam

G

17%

Reading Plans and Specifications

Construction drawings, architectural/engineering symbols, shop drawings, specifications, ADA requirements.

~10 questions on the exam

Study Strategy for Project Mgmt

Prioritize by Weight

Focus on Construction (63%) and Safety (20%) first — they cover the most questions.

Tab Your References

With only 4.5 min/question, you need to find answers fast. Color-code tabs by content area.

Master the Math

Calculation questions (payroll, overhead, bidding) are common. Practice with our math calculator until the formulas are second nature.

Know Your Statutes

State-specific laws and regulations are heavily tested. Bookmark these sections in your reference books for quick lookup.

Simulate Exam Conditions

Take timed 60-question practice sessions to build stamina for the 4.5-hour exam.

Review Wrong Answers

Use the wrong book feature to revisit missed questions. Understanding why an answer is wrong is as important as knowing the right answer.

Frequently Asked Questions

How many questions are on the Project Management exam?

The Project Management exam contains 60 scored questions. You must answer them within 4.5 hours. The exam is administered by Pearson VUE and is open book — you may bring approved reference materials.

What is the passing score for Project Mgmt?

You need a score of 70% or higher to pass the Project Management exam. That means you must answer at least 42 out of 60 questions correctly.

Is the Project Mgmt exam open book?

Yes. The Project Mgmt contractor exam is open book. You are allowed to bring approved reference books into the testing center. However, time management is critical — you cannot look up every answer.

How long do I have to complete the Project Mgmt exam?

You have 4.5 hours (270 minutes) to complete all 60 questions. That averages to about 4.5 minutes per question.

Master Project Mgmt

Practice all 1120 questions interactively with progress tracking and adaptive difficulty.

Start Free Practice

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.