A Sarasota trench will be 6 ft deep and employees must enter it. Which planning item is normally required unless the excavation is entirely in stable rock?
Correct Answer
B) protective system
A protective system is required for employee entry at the stated trench depth unless an exception applies.
Why This Is the Correct Answer
A protective system is required for employee entry at the stated trench depth unless an exception applies.
Why the Other Options Are Wrong
Option A: a second exit at each end
a second exit at each end may relate to another site control, but it does not remove or guard the excavation protective system exposure being tested.
Option C: daily air monitoring inside
daily air monitoring inside may relate to another site control, but it does not remove or guard the excavation protective system exposure being tested.
Option D: a spotter at the trench edge
a spotter at the trench edge may relate to another site control, but it does not remove or guard the excavation protective system exposure being tested.
Memory Technique
Hazard lock for Superintendent Plans: controlling is the harm, employee is the guard.
Reference Hint
Open-book path: tab OSHA 29 CFR 1926 to Subpart P, 1926.652 Requirements for protective systems; verify the OSHA safety threshold or jobsite control before answering.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During the pre-installation review, the field issue is that the project condition shows that movement or separation is intended. Which bond breaker material is the best match?
Next Question
The construction team is coordinating a method decision because accepted work still needs protection. Which closeout method is best?