EstatePass
Project MgmtBlueprintsmedium17% of exam part

From the plumbing fixture schedule, what waste size is listed for UR-1?

Correct Answer

C) 2 in

UR-1 lists a 2 in waste.

Answer Options
A
1-1/4 in
B
4 in
C
2 in
D
3 in

Why This Is the Correct Answer

UR-1 lists a 2 in waste.

Why the Other Options Are Wrong

Option A: 1-1/4 in

1-1/4 in skips the written authority, scope, price, notice, or release control needed for plumbing schedule lookup.

Option B: 4 in

4 in skips the written authority, scope, price, notice, or release control needed for plumbing schedule lookup.

Option D: 3 in

3 in skips the written authority, scope, price, notice, or release control needed for plumbing schedule lookup.

Memory Technique

Restroom Rough-In shortcut is not a term until paper carries it.

Reference Hint

Open-book path: turn to sheet P-503 in the plan packet, then use the PLUMBING FIXTURE SCHEDULE - RESTROOMS note/table before checking P&P Commercial Construction plan-reading guidance.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.