A Lakeland excavation has this condition before entry: rain occurred before the morning shift. Which safety step is required before work proceeds?
Correct Answer
C) competent-person inspection
Excavations require competent-person inspections when conditions could affect employee safety.
Why This Is the Correct Answer
Excavations require competent-person inspections when conditions could affect employee safety.
Why the Other Options Are Wrong
Option A: enter since the rain stopped
enter since the rain stopped may relate to another site control, but it does not remove or guard the excavation competent-person inspection exposure being tested.
Option B: any worker glances first
any worker glances first may relate to another site control, but it does not remove or guard the excavation competent-person inspection exposure being tested.
Option D: wait for the soil to dry
wait for the soil to dry may relate to another site control, but it does not remove or guard the excavation competent-person inspection exposure being tested.
Memory Technique
Hazard lock for the controlling choice: excavations is the harm, inspections is the guard.
Reference Hint
Open-book path: tab OSHA 29 CFR 1926 to Subpart P, 1926.651(k) Inspections; verify the OSHA safety threshold or jobsite control before answering.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass