The Palm Bay project has this confined-space condition: crew will enter a manhole with limited entry. Which safety control should be completed before entry?
Correct Answer
D) confined-space entry evaluation
Confined-space work requires evaluation, atmospheric controls, and rescue planning before entry.
Why This Is the Correct Answer
Confined-space work requires evaluation, atmospheric controls, and rescue planning before entry.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the area summary schedule, what occupancy is listed for Zone D?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
In the look-ahead meeting, the constraint is that finished surfaces need compatible protection. Which protection material should the project team carry?
Next Question
In the look-ahead meeting, the constraint is that the controlling field constraint is that cleaning must match units and mortar. Which masonry cleaning method should the project team carry?
