While preparing the preconstruction estimate lock for the campus maintenance annex, the planter-wall back face measures 1961 SF before a 7% waste allowance. Each protection-board panel covers 24 SF. How many panels should be ordered?
Correct Answer
A) 88 panels
Order quantity equals area times waste factor divided by 24 SF coverage, rounded up.
Why This Is the Correct Answer
Order quantity equals area times waste factor divided by 24 SF coverage, rounded up.
Why the Other Options Are Wrong
Option B: 82 panels
82 panels is below the supported result for waterproofing protection board; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 92 panels
92 panels is above the supported result for waterproofing protection board; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 89 panels
89 panels is above the supported result for waterproofing protection board; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Estimator Checks takeoff: count the condition before counting the package Tie the cue to Waterproofing Protection Board Estimator.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Waterproofing methods; protection board coverage; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?