A Clearwater lift plan has this rigging issue: sling tag is unreadable. Which safety action applies before the pick?
Correct Answer
C) rigging inspection hold
Rigging must be inspected, load weights confirmed, and damaged gear removed before lifting.
Why This Is the Correct Answer
Rigging must be inspected, load weights confirmed, and damaged gear removed before lifting.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During the field-takeoff reconciliation at the seafood-market cooler room, the roof edge zone for ice-and-water membrane covers 22300 SF, with 10% added for laps and cuts. Each roll covers 225 SF. How many rolls are needed?
Next Question
The Ocala work area has this housekeeping condition: debris blocks the emergency route. Which safety correction should be made?