During the pre-installation review, the field issue is that the work should be released only if the team addresses that bolt condition follows connection requirements. Which bolting method is the best match?
Correct Answer
B) Coordinate specified snug-tight or pretensioned bolting
specified snug-tight or pretensioned bolting best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why This Is the Correct Answer
specified snug-tight or pretensioned bolting best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why the Other Options Are Wrong
Option A: Coordinate turn-of-nut pretensioning
Coordinate turn-of-nut pretensioning addresses a neighboring field issue, but not the condition or method control required for structural steel bolting.
Option C: Field method: Coordinate calibrated wrench pretensioning
Field method: Coordinate calibrated wrench pretensioning addresses a neighboring field issue, but not the condition or method control required for structural steel bolting.
Option D: Coordinate twist-off tension-control bolts
Coordinate twist-off tension-control bolts addresses a neighboring field issue, but not the condition or method control required for structural steel bolting.
Memory Technique
The field condition asks; structural steel bolting answers in work boots for Manager Checking.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Structural steel methods; bolt installation and inspection; verify the construction method, material selection, equipment choice, or work sequence that fits the field condition.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Related Study Resources
Previous Question
For the subcontractor quantity check at the hospital dietary expansion, the non-shrink grout requires 11.5 CY of base-plate pockets. If each bag yields 0.45 CY, how many bags are needed?
Next Question
At the grocery receiving dock, during the subcontractor quantity check, the deck repair area for plywood roof sheathing is 9040 SF. With 12% waste and 32 SF per sheet or panel, how many sheets are required?
