A steel connection schedule identifies which joints require snug-tight installation and which require pretensioning. Which approach follows that schedule?
Correct Answer
B) Use the scheduled joint condition and approved installation method
Apply the required condition to each joint using an approved installation and inspection procedure. Turn-of-nut, calibrated wrench and tension-control systems may be valid when specified; none is a universal substitute for the connection requirements.
Why This Is the Correct Answer
Apply the required condition to each joint using an approved installation and inspection procedure. Turn-of-nut, calibrated wrench and tension-control systems may be valid when specified; none is a universal substitute for the connection requirements.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Project Mgmt Questions
A sloped roof surface measures 7,360 square feet. Add 8% waste and express the result in 100-square-foot roofing squares, to the nearest 0.1 square.
Grinding metal creates flying-particle hazards to a worker’s eyes and face. Which PPE action addresses those hazards?
The project inspection plan requires in-wall rough-in approval before gypsum board conceals stud cavities. Which coordination item must be completed before close-in?
A low-slope roof detail requires base flashing continuous with the field membrane before its upper edge is counterflashed. The membrane-to-wall transition is not yet installed. Which listed step addresses that missing interface?
A membrane takeoff covers 13,720 square feet before 8% waste. Express the adjusted area in 100-square-foot roofing squares, to the nearest 0.1 square.
An office needs carpet tile over 9,975 square feet, plus one combined 15% allowance for waste and spare stock. Each carton supplies 48 square feet. How many whole cartons are needed?
A grout takeoff requires 11.5 cubic feet including its allowance. For this exercise, each bag yields 0.45 cubic foot. How many whole bags are needed?
A sling’s required safe-working-load identification is illegible before a planned lift. Which action is required?
A supplied metal-deck takeoff calls for 18 approved pins per sheet over 175 sheets. Boxes contain 900 pins. With no additional allowance, how many whole boxes are required?
A metal-deck connection schedule specifies support attachments and side-lap fasteners. Which approach ensures installation follows the complete design?