For the buyout verification pass at the school band-room storage, the partition run is 114 ft long and studs are placed at 12 ft on center, including one at the starting end. How many studs are needed?
Correct Answer
A) 10 studs
Count the spaces along the run, then include the starting item.
Why This Is the Correct Answer
Count the spaces along the run, then include the starting item.
Why the Other Options Are Wrong
Option B: 11 studs
11 studs is above the supported result for metal stud layout; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option C: 12 studs
12 studs is above the supported result for metal stud layout; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 13 studs
13 studs is above the supported result for metal stud layout; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Metal Stud Layout cart for Foreman Checks: count first, spaces second, whole units last.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Cold-formed framing; stud spacing takeoff; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass