The Daytona Beach job has this temporary-power condition: wet work area uses cord-connected equipment. Which safety control should the superintendent verify?

Correct Answer

B) wet-area electrical protection

Construction temporary power must control shock exposure through GFCI or an allowed assured equipment grounding program.

Answer Options
A
elevate the cords only
B
wet-area electrical protection
C
dry it and skip GFCI
D
a wet-area caution sign

Why This Is the Correct Answer

Construction temporary power must control shock exposure through GFCI or an allowed assured equipment grounding program.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.