In the look-ahead meeting, the constraint is that long-lead item needs early coordinated release. Which procurement sequence should the project team carry?
Correct Answer
D) verify submittal and lead time before release
verify submittal and lead time before release best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why This Is the Correct Answer
verify submittal and lead time before release best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why the Other Options Are Wrong
Option A: order from preliminary sketch only
order from preliminary sketch only skips the written authority, scope, price, notice, or release control needed for sequencing long-lead material.
Option B: wait until installation week to order
wait until installation week to order skips the written authority, scope, price, notice, or release control needed for sequencing long-lead material.
Option C: Field method: substitute in field after delay appears
Field method: substitute in field after delay appears skips the written authority, scope, price, notice, or release control needed for sequencing long-lead material.
Memory Technique
When controlling clashes with condition, let the contract speak before Foreman Selecting.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Construction methods; procurement and sequence coordination; verify the construction method, material selection, equipment choice, or work sequence that fits the field condition.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During the material-order review at the urgent-care ambulance canopy, the deck area for the temporary dry-in totals 1840 SF. With 15% waste, how many roofing squares are needed?
Next Question
A St. Augustine worker finds an extension cord with this defect: cord is repaired with tape only. Which action is safest before use continues?