Before releasing the work, the team identifies this condition: the controlling field constraint is that frame must be mechanically anchored. Which opening anchorage fits best?
Correct Answer
C) Select specified frame anchors and backing
specified frame anchors and backing best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why This Is the Correct Answer
specified frame anchors and backing best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why the Other Options Are Wrong
Option A: Select finish nails through hollow metal frame
Select finish nails through hollow metal frame addresses a neighboring field issue, but not the condition or method control required for door frame anchorage.
Option B: Select foam only as structural anchorage
Select foam only as structural anchorage addresses a neighboring field issue, but not the condition or method control required for door frame anchorage.
Option D: Select grout placed before anchors are set
Select grout placed before anchors are set addresses a neighboring field issue, but not the condition or method control required for door frame anchorage.
Memory Technique
Controlling is the clue; condition is the method check for Manager Checking Tie the cue to Door Anchorage Manager Checking.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Openings methods; frame anchorage and grout coordination; verify the construction method, material selection, equipment choice, or work sequence that fits the field condition.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
In the look-ahead meeting, the constraint is that finishing should not trap bleed water. Which finishing decision should the project team carry?
Next Question
The Hialeah crane pick has this communication condition: operator cannot see the landing area. Which safety control should be used?
