In the look-ahead meeting, the constraint is that finishing should not trap bleed water. Which finishing decision should the project team carry?
Correct Answer
B) wait until bleed water dissipates
wait until bleed water dissipates best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why This Is the Correct Answer
wait until bleed water dissipates best matches the stated condition. The other choices are real construction options in the same family, but they fit different field conditions.
Why the Other Options Are Wrong
Option A: finish while bleed water is present
finish while bleed water is present belongs to a different file or record trail; it does not prove the bleed water finishing event.
Option C: dust cement to absorb bleed water
dust cement to absorb bleed water belongs to a different file or record trail; it does not prove the bleed water finishing event.
Option D: seal surface before bleed water exits
seal surface before bleed water exits belongs to a different file or record trail; it does not prove the bleed water finishing event.
Memory Technique
File Foreman Selecting where the next reviewer would look first.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Concrete finishing methods; bleed water and surface timing; verify the construction method, material selection, equipment choice, or work sequence that fits the field condition.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During the buyout verification pass at the plant-nursery sales canopy, a trench drain has a 132 ft run at 0.50% slope. What fall across the run is required in inches?
Next Question
Before releasing the work, the team identifies this condition: the controlling field constraint is that frame must be mechanically anchored. Which opening anchorage fits best?