The Boca Raton work area has this housekeeping condition: debris blocks the emergency route. Which safety correction should be made?
Correct Answer
A) clear access route
Housekeeping controls keep access routes clear, remove trip hazards, and control protruding nails.
Why This Is the Correct Answer
Housekeeping controls keep access routes clear, remove trip hazards, and control protruding nails.
Why the Other Options Are Wrong
Option B: mark it with caution tape
mark it with caution tape may relate to another site control, but it does not remove or guard the housekeeping safety exposure being tested.
Option C: use an alternate exit
use an alternate exit may relate to another site control, but it does not remove or guard the housekeeping safety exposure being tested.
Option D: clean it up at week end
clean it up at week end may relate to another site control, but it does not remove or guard the housekeeping safety exposure being tested.
Memory Technique
Name the harm before the guard; mark, caution, tape cannot stand in for Foreman Corrects.
Reference Hint
Open-book path: tab OSHA 29 CFR 1926 to Subpart C, 1926.25 Housekeeping; verify the OSHA safety threshold or jobsite control before answering.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?