Electrical rough-in will conflict with fire-sprinkler mains unless the trades coordinate above the corridor ceiling. What should the GC do?
Correct Answer
B) Coordinate layout and sequencing before installation so rework is avoided
Field operations require coordination of trades before work is installed in conflicting locations.
Why This Is the Correct Answer
Field operations require coordination of trades before work is installed in conflicting locations.
Why the Other Options Are Wrong
Option A: Install both systems immediately and correct conflicts after ceiling closure
Install both systems immediately and correct conflicts after ceiling closure may relate to another site control, but it does not remove or guard the trade coordination exposure being tested.
Option C: Let the first trade on site control all other work without review
Let the first trade on site control all other work without review may relate to another site control, but it does not remove or guard the trade coordination exposure being tested.
Option D: Wait until the certificate of occupancy meeting to resolve the conflict
Wait until the certificate of occupancy meeting to resolve the conflict may relate to another site control, but it does not remove or guard the trade coordination exposure being tested.
Memory Technique
Trade Coordination lock for Tenant Build-Out: field is the harm, operations is the guard.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Construction procedures; trade coordination and sequencing; match the project role and timing before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
Next Question
Temporary water service costs $390 per month for 8 months plus a $1,150 connection charge. What total should be carried?