The architect rejects a portion of installed finish work. What field-control action helps manage correction?

Correct Answer

B) Log the nonconformance, assign correction responsibility, and track verification

Nonconforming work should be tracked through correction and verification.

Answer Options
A
Remove the rejection from the record because it may affect payment and subcontractor billing status
B
Log the nonconformance, assign correction responsibility, and track verification
C
Wait until warranty expiration before deciding whether correction is needed
D
Treat the rejection as bid withdrawal by the original subcontractor

Why This Is the Correct Answer

Nonconforming work should be tracked through correction and verification.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.