A Florida GC finds a conflict between a plan note and the specifications during buyout. Under AIA A201, what should the GC do with the Contract Documents?
Correct Answer
A) Treat them as complementary and seek interpretation instead of choosing one unilaterally
A201 treats the Contract Documents as complementary and provides a process for interpretation rather than unilateral selection.
Why This Is the Correct Answer
A201 treats the Contract Documents as complementary and provides a process for interpretation rather than unilateral selection.
Why the Other Options Are Wrong
Option B: Treat the larger drawing scale as automatically voiding all written specifications
Treat the larger drawing scale as automatically voiding all written specifications skips the written authority, scope, price, notice, or release control needed for contract documents.
Option C: Ignore the conflict until final payment because buyout is outside the contract
Ignore the conflict until final payment because buyout is outside the contract skips the written authority, scope, price, notice, or release control needed for contract documents.
Option D: Let the lowest subcontractor decide the conflict based on the cheapest interpretation and issue pricing on that basis
Let the lowest subcontractor decide the conflict based on the cheapest interpretation and issue pricing on that basis skips the written authority, scope, price, notice, or release control needed for contract documents.
Memory Technique
Office Build-Out shortcut is not a term until paper carries it.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 1, Β§1.2 Correlation and Intent of the Contract Documents; match the contract role and timing in the stem before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A base course requires 1,440 compacted tons. The estimator carries 3.5% waste and loss. How many tons should be ordered?
Next Question
A Florida contract is silent on a listed tax that was legally enacted when bids were received. Under AIA A201, who normally carries that tax for the Work?