A Florida contract is silent on a listed tax that was legally enacted when bids were received. Under AIA A201, who normally carries that tax for the Work?
Correct Answer
A) The Contractor pays applicable sales, consumer, use, and similar taxes legally enacted at bid time
A201 addresses taxes legally enacted when bids are received or negotiations concluded.
Why This Is the Correct Answer
A201 addresses taxes legally enacted when bids are received or negotiations concluded.
Why the Other Options Are Wrong
Option B: The Architect pays the tax because pay applications are reviewed by the architect, and use that shortcut to decide the enacted legally requirement, while treating the inspection card as a contract amendment
The Architect pays the tax because pay applications are reviewed by the architect, and use that shortcut to decide the enacted legally requirement, while treating the inspection card as a contract amendment puts the item in the wrong financial bucket, timing, base, or comparison for taxes.
Option C: The Owner's lender pays the tax separately without a contract allowance
The Owner's lender pays the tax separately without a contract allowance puts the item in the wrong financial bucket, timing, base, or comparison for taxes.
Option D: The final inspector assigns the tax to whichever trade is on site last, and treat owner occupancy as acceptance of the procedure
The final inspector assigns the tax to whichever trade is on site last, and treat owner occupancy as acceptance of the procedure puts the item in the wrong financial bucket, timing, base, or comparison for taxes.
Memory Technique
An unlabeled Reviews Whether dollar tells the wrong story.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 3, Β§3.6 Taxes; match the contract role, notice step, and timing in the stem before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A Florida GC finds a conflict between a plan note and the specifications during buyout. Under AIA A201, what should the GC do with the Contract Documents?
Next Question
A crew installs 18 hollow-metal frames per day. The project has 72 frames. At $1,260 per crew day, what labor amount should be carried?
