A base course requires 1,440 compacted tons. The estimator carries 3.5% waste and loss. How many tons should be ordered?

Correct Answer

B) 1,490 tons

Apply the waste and loss factor to required compacted tons.

Answer Options
A
1,389 tons
B
1,490 tons
C
1,440 tons
D
1,520 tons

Why This Is the Correct Answer

Apply the waste and loss factor to required compacted tons.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.