The owner asks who is authorized to receive day-to-day communications for the contractor at the site. Which AIA A201 role fits?

Correct Answer

D) The Contractor's superintendent as site representative

A201 requires the Contractor to employ a competent superintendent and makes that person the contractor's representative at the site.

Answer Options
A
The unsuccessful bidder listed on the bid tab, without distinguishing a clarification from a change in price or time
B
The supplier who fabricated the largest stored material item
C
The permit clerk who accepted the inspection request
D
The Contractor's superintendent as site representative

Why This Is the Correct Answer

A201 requires the Contractor to employ a competent superintendent and makes that person the contractor's representative at the site.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.