Contract AdminContractsmedium40% of exam part

A monthly pay application includes stored materials and completed work. Under AIA A201, who certifies payment to the Owner after review?

Correct Answer

B) The Architect certifies the amount properly due based on the application

A201 provides for architect review and certification of amounts due in the payment process.

Answer Options
A
The lowest bidder certifies payment because it established original pricing
B
The Architect certifies the amount properly due based on the application
C
The permit inspector certifies all contract payment amounts for the Owner
D
The material supplier certifies final completion for the full project

Why This Is the Correct Answer

A201 provides for architect review and certification of amounts due in the payment process.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.