A weekly coordination meeting resolves a sequencing issue that affects three trades. What should the PM do after the meeting?

Correct Answer

D) Publish accurate meeting minutes with action items, responsibilities, and due dates

Meeting minutes preserve coordination decisions and assignments.

Answer Options
A
Rely only on memory because meeting minutes are used only before award and not during construction
B
Wait until final payment to tell the trades what was decided
C
Ask the supplier to issue the official design interpretation
D
Publish accurate meeting minutes with action items, responsibilities, and due dates

Why This Is the Correct Answer

Meeting minutes preserve coordination decisions and assignments.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.