After permit issuance, the owner approves a structural detail change. What should happen before the revised work is built?
Correct Answer
C) Submit the revised documents for required approval by the building department
Permit documents must match approved work; revised work commonly requires submitted and approved revisions.
Why This Is the Correct Answer
Permit documents must match approved work; revised work commonly requires submitted and approved revisions.
Why the Other Options Are Wrong
Option A: Build the change first and mention it during final payment
Build the change first and mention it during final payment skips the written authority, scope, price, notice, or release control needed for permit revisions.
Option B: Let the lowest subcontractor decide whether the permit needs updating and document the decision only in its proposal
Let the lowest subcontractor decide whether the permit needs updating and document the decision only in its proposal skips the written authority, scope, price, notice, or release control needed for permit revisions.
Option D: Treat the change order as automatic code approval
Treat the change order as automatic code approval skips the written authority, scope, price, notice, or release control needed for permit revisions.
Memory Technique
Permit Revisions square for Changes Permitted: scope, authority, price, paper.
Reference Hint
Open-book path: tab Florida Building Code, Building, 8th Edition (2023), Chapter 1 Administration to Chapter 1, §107 Construction Documents; §105 Permits; match the project role and timing before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
