After permit issuance, the owner approves a structural detail change. What should happen before the revised work is built?

Correct Answer

C) Submit the revised documents for required approval by the building department

Permit documents must match approved work; revised work commonly requires submitted and approved revisions.

Answer Options
A
Build the change first and mention it during final payment
B
Let the lowest subcontractor decide whether the permit needs updating and document the decision only in its proposal
C
Submit the revised documents for required approval by the building department
D
Treat the change order as automatic code approval

Why This Is the Correct Answer

Permit documents must match approved work; revised work commonly requires submitted and approved revisions.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.