A direct contract exceeds $5,000 and the first inspection is approaching. What must be filed with the issuing authority before that inspection can be approved?
Correct Answer
D) File the required recorded notice copy or recording information
Florida lien law ties required notice-of-commencement documentation to inspections for covered direct contracts.
Why This Is the Correct Answer
Florida lien law ties required notice-of-commencement documentation to inspections for covered direct contracts.
Why the Other Options Are Wrong
Option A: A final lien waiver from every material supplier before any work has been inspected
A final lien waiver from every material supplier before any work has been inspected skips the written authority, scope, price, notice, or release control needed for notice of commencement timing.
Option B: A subcontract bid tab showing the three lowest quotes for each trade
A subcontract bid tab showing the three lowest quotes for each trade skips the written authority, scope, price, notice, or release control needed for notice of commencement timing.
Option C: An owner's punch list signed after occupancy and final cleaning
An owner's punch list signed after occupancy and final cleaning skips the written authority, scope, price, notice, or release control needed for notice of commencement timing.
Memory Technique
When lien clashes with law, let the contract speak before Coordinates Permit.
Reference Hint
Open-book path: tab Florida Statutes Chapter 713 to Section 713.135 notice of commencement and building permits; confirm the required quantity, authority, timing, or record before selecting the answer.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
