The owner verbally asks for a small added task during a site walk. What is the best field-administration response before doing the work?
Correct Answer
D) Document the request and obtain the required written direction or change authorization
Field changes should be documented and authorized through the contract process.
Why This Is the Correct Answer
Field changes should be documented and authorized through the contract process.
Why the Other Options Are Wrong
Option A: Proceed from memory and price it at closeout without records, signatures, or written direction
Proceed from memory and price it at closeout without records, signatures, or written direction belongs to a different file or record trail; it does not prove the field change record event.
Option B: Use the daily weather report as the owner's authorization
Use the daily weather report as the owner's authorization belongs to a different file or record trail; it does not prove the field change record event.
Option C: Ask a supplier to approve the owner-directed scope
Ask a supplier to approve the owner-directed scope belongs to a different file or record trail; it does not prove the field change record event.
Memory Technique
A record works only when it proves the exact changes event for Owner Asks.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Field administration; change documentation and authorization; match the role, timing, and required approval before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?