Construction debris from the contractor's work is interfering with an occupied corridor. Which AIA A201 responsibility applies?
Correct Answer
D) Cleanup responsibility
A201 includes cleanup responsibilities during and at completion of the Work.
Why This Is the Correct Answer
A201 includes cleanup responsibilities during and at completion of the Work.
Why the Other Options Are Wrong
Option A: Architect certification of bid security
Architect certification of bid security skips the written authority, scope, price, notice, or release control needed for cleaning.
Option B: Owner issuance of shop drawings
Owner issuance of shop drawings skips the written authority, scope, price, notice, or release control needed for cleaning.
Option C: Supplier control of final completion
Supplier control of final completion skips the written authority, scope, price, notice, or release control needed for cleaning.
Memory Technique
Cleaning square for Retail Renovation: scope, authority, price, paper.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 3 Section 3.15 Cleaning Up; match the AIA role, timing, and contract instrument to the facts.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The owner verbally asks for a small added task during a site walk. What is the best field-administration response before doing the work?
Next Question
A subcontractor's scope changes because the owner approved a related prime contract change. Under AIA A401, what should the GC administer?
