A subcontractor's scope changes because the owner approved a related prime contract change. Under AIA A401, what should the GC administer?

Correct Answer

C) A corresponding subcontract change consistent with the subcontract documents

A401 includes provisions for changes in subcontract work corresponding to prime contract changes.

Answer Options
A
Free changed work because the owner issued the prime change, and treat the project meeting agenda as the contract instrument
B
Use of the original bid bond as subcontract change authorization
C
A corresponding subcontract change consistent with the subcontract documents
D
No subcontract impact review until final payment is assembled

Why This Is the Correct Answer

A401 includes provisions for changes in subcontract work corresponding to prime contract changes.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.