A payment dispute is pending, but no stop-work right has been triggered. Which AIA A201 concept should the GC remember?

Correct Answer

A) Continue performance during claim administration when required

A201 includes claim administration concepts requiring continued performance unless the contract provides otherwise.

Answer Options
A
Continue performance during claim administration when required
B
Stop all work automatically whenever any claim is submitted
C
Convert the claim into a bid withdrawal before award
D
Treat mediation as final completion of the Work, and using field preference as if it were written authorization

Why This Is the Correct Answer

A201 includes claim administration concepts requiring continued performance unless the contract provides otherwise.

Why the Other Options Are Wrong

Option B: Stop all work automatically whenever any claim is submitted

Stop all work automatically whenever any claim is submitted skips the written authority, scope, price, notice, or release control needed for continuing performance.

Option C: Convert the claim into a bid withdrawal before award

Convert the claim into a bid withdrawal before award skips the written authority, scope, price, notice, or release control needed for continuing performance.

Option D: Treat mediation as final completion of the Work, and using field preference as if it were written authorization

Treat mediation as final completion of the Work, and using field preference as if it were written authorization skips the written authority, scope, price, notice, or release control needed for continuing performance.

Memory Technique

Continuing Performance square for Has Disputed: scope, authority, price, paper.

Reference Hint

Open-book path: tab AIA A201-2017 to Article 15, Section 15.1 Claims and continuing performance; compare the role, timing, and required instrument in the stem.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.