Contract AdminPreconstructionmedium27% of exam part

A subcontractor gives one combined price for two alternates that the bid form requires separately. What should the estimator do?

Correct Answer

B) Clarify alternates separately

Bid forms require prices in the requested structure for evaluation.

Answer Options
A
Put the combined number under both alternates
B
Clarify alternates separately
C
Delete the alternate that is harder to separate
D
Resolve the split after final completion

Why This Is the Correct Answer

Bid forms require prices in the requested structure for evaluation.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.