A field question may affect layout and cost. What should the project manager use to keep the issue controlled?
Correct Answer
C) A formal RFI tracked in the project log until the answer is received and distributed
Formal RFIs and logs control questions, responses, and distribution.
Why This Is the Correct Answer
Formal RFIs and logs control questions, responses, and distribution.
Why the Other Options Are Wrong
Option A: A verbal note with no record because RFIs slow the work and the field crew can interpret the answer later
A verbal note with no record because RFIs slow the work and the field crew can interpret the answer later skips the written authority, scope, price, notice, or release control needed for rfi log.
Option B: A final pay application line with no design response
A final pay application line with no design response skips the written authority, scope, price, notice, or release control needed for rfi log.
Option D: A subcontractor invoice as the designer's answer
A subcontractor invoice as the designer's answer skips the written authority, scope, price, notice, or release control needed for rfi log.
Memory Technique
Rfi Log square for Receives Layout: scope, authority, price, paper.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Construction administration; RFI procedure and tracking; match the project role and timing before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?